A set of high gloss lacquer cabinets rarely fails because of the finish. It fails because four or five people sign off at different moments, each looking at something different. Interior designer, homeowner or developer, builder or site contractor, procurement and sometimes a finance approver all touch the same run of doors. This guide sets out who approves what, in which order, and what has to be on the table before each signature, so the joinery is not the thing that holds up your handover.
Why lacquered cabinetry needs a tighter approval chain than most finishes
High gloss surfaces are unforgiving. A reflected sheen shows every difference in panel angle, edge treatment and light position, so two people can stand in the same kitchen and disagree about whether it looks right. On top of that, our made-to-measure work is built to project-specific dimensions and finish selections, which means a late change does not swap a stock item on a shelf; it restarts panel production and pushes the delivery date.
The practical consequence: approvals have to be split into separate decisions rather than bundled into one big "is the kitchen approved?" meeting. Colour, layout and hardware are three different conversations with three different owners of risk.
Map the five roles before you send a single sample
- Interior designer or design lead — owns finish, proportion, handle style and how the cabinetry reads against worktops, splashbacks and lighting.
- Client decision-maker — homeowner, developer or asset owner. Signs the look and the budget; usually the person who changes their mind last.
- Builder or site contractor — owns the openings, floor level, wall flatness, services and the sequence that lets cabinetry go in without damaging other trades.
- Procurement or project manager — owns the order date, delivery window, container plan and who pays for what.
- Facilities or end user — the person who will actually open these doors every day. Often left out of design meetings, then consulted at handover.
Write these names down in one line each before the first drawing is issued. If you cannot name a person for one of the five roles, that gap is your likely delay later.
Run four separate sign-offs instead of one
| Stage | What is approved | Who signs | What must be in front of them |
|---|---|---|---|
| 1. Design intent | Finish family, gloss level, door profile, colour direction | Design lead plus client | Physical lacquer samples and a rendered room view, not a screenshot |
| 2. Layout and interface | Cabinet layout, appliance positions, clearances, worktop edge | Design lead plus builder | Dimensioned elevations and floor plan with services marked |
| 3. Technical specification | Made-to-measure sizes, material and finish selection, interior configuration | Procurement plus builder | Confirmed site dimensions, opening tolerances, selected hardware |
| 4. Commercial release | Final quantity, order date, delivery address, Incoterms | Procurement plus budget holder | Priced order summary and the production cut-off date |
The rule that keeps this honest: once stage 3 is signed, dimensions are frozen. Anything after that is a change order with a named cost and a named effect on the delivery date, agreed in writing by the same people who signed stage 3.
Give every approver a deadline they can see
Silence is the most common cause of slippage on custom joinery. Set one review window per stage, name one person responsible for closing it, and put the production cut-off date at the top of the sheet so everyone understands what "late" means. When a decision-maker cannot attend, agree in advance who may sign in their place; a delegated signature recorded in the same document prevents a design being reopened after panels are already in production.
Where our team sits inside your approval chain
SANTERSON has manufactured furniture and building materials since 2008, supplying project customers across hospitality, villa and office work. For cabinetry we work from drawings rather than catalogues: interior design services cover space planning, layout and 3D visual renderings, so your designer has something to present at stage 1 and something for the builder to check at stage 2. Custom & OEM service covers bespoke finishes and prototyping when a project needs a specific colour or texture rather than a standard option.
Downstream, logistics and door-to-door delivery covers freight by sea, air and rail with customs paperwork and container loading, and installation and after-sales support covers site fitting and inspection. That matters for approvals because it means the same supplier answers for production, delivery and fitting — one set of drawings travels all the way to site instead of being reinterpreted at each handover.
The lacquer range is not limited to kitchens either. The same finish family appears in high gloss lacquer wardrobes, so a bedroom run can be approved against the same sample board as the kitchen and avoid a second round of colour sign-off.
Before you release an order: confirm the site dimensions, the selected finish and hardware, the delivery address and the production cut-off date in one signed sheet. If any of those four is still open, the order is not ready to place.
Questions approvers ask us most often
Can we change the colour after samples are approved? Yes, up to the point dimensions and specification are signed. After that it is treated as a change order, because lacquered panels are produced to the agreed selection.
Who checks that the walls and floor will actually fit the cabinetry? The builder or site contractor at stage 2. We build to the confirmed dimensions you supply, so flatness and level need verifying on site before those dimensions are frozen.
What if two rooms use the same finish? Order them on one specification sheet and one production batch wherever possible, so colour and sheen match across the kitchen, wardrobes and any other lacquered joinery in the project.
Do we need a local agent to manage this? No. One project contact handles drawings, specification, freight documentation and installation coordination, which keeps the approval trail in a single thread rather than split across several vendors.