A door submittal is the package a contractor, designer or project owner reviews before a door schedule becomes a manufactured set of openings. For a made-to-measure item such as our Classic French Double Doors, the submittal is where misunderstandings get settled — glazing, swing direction, finish, frame condition and site dimensions are all fixed on paper before production starts. The list below follows the order most project teams work in: identify the opening, fix the hardware, then confirm finishes, packaging and site support.
1. Project Identification and Door Schedule Reference
Every sheet in the package should carry the same reference information, because door sets are usually reviewed alongside a full door schedule rather than on their own. Include:
- Project name, delivery destination and the internal purchase order or lot number
- The door tag from the schedule, for example D-01, plus the room or elevation it belongs to
- Quantity per tag, so a pair of doors is not read as two single leaves
- Issue date and revision number of the drawing set you are working from
Where the specification names a product family rather than a fixed model, state which collection you are proposing. Our Santerson Arched French Doors and Santerson Modern Slim Frame French Doors sit in the same French doors category but produce visibly different elevations, so the collection name belongs on the cover sheet.
2. Dimensional Drawings and Tolerances
French double doors fail on site far more often through dimension than through appearance. The submittal should show:
- Rough opening width and height at head, middle and sill for each opening — measured on site, not taken from a drawing scale
- Finished leaf size, frame section depth and the frame rebate, drawn to scale
- Stile and rail widths, and the muntin or glazing-bar layout with its spacing
- Threshold and floor finish levels, including any change in finished floor height across the opening
- Which dimensions are fixed by the building and which we can adjust during manufacturing
These doors are supplied to project-specific sizes, so the confirmed drawing is the production reference. State the tolerance you will work to on each dimension and record who signed off the measured sizes. If a site opening sits outside the agreed range, that note belongs in the submittal before order confirmation, not in an email after production has started.
3. Material, Finish and Glazing Construction
The specification sheet should describe the build-up rather than a marketing name:
- Leaf and frame substrate, and how it is finished — paint, lacquer, veneer or laminate
- Colour or grain reference with a physical sample number, since screen colours do not reproduce timber grain or sheen
- Glazing type, thickness and whether panes are fixed or removable, plus the glazing bar profile
- Whether glass is clear, low-iron, frosted, patterned or tinted, and which face each pane sits on
- Edge treatment on any visible stile, and how the frame meets the wall finish
4. Hardware Schedule and Hinge Preparation
Hardware decisions change the door itself, so they cannot wait until the doors arrive. The submittal should carry:
- Active and passive leaf designation, plus which way each leaf swings and which hand it hangs on
- Hinge type, count, position and mortice detail, including any offset needed for the floor covering
- Lock, keep, handle set and any flush bolt or astragal on the passive leaf
- Door closer or holder if specified, and whether the frame needs preparation for it
- Whether hardware is supplied with the doors or by others, and who prepares the openings for it
If a handleless or concealed detail is required, submit a section through the leaf edge so the gap allowance is agreed in writing. Concealed and flush details depend on frame preparation done at the factory, and that preparation cannot be reversed on site.
5. Samples, Approvals and Sign-Off Record
State what physically exists for approval and where it is: a finished corner sample or mock-up leaf, a glazing sample, and a hardware set mounted for inspection. The submittal then records the approval trail — who reviewed each item, the date, and any condition attached. A conditional approval that is not written into the package turns into a dispute at handover.
6. Packaging, Delivery Sequence and Site Handling
Double doors are heavy, and glazed leaves are the fragile part. Cover:
- Packaging build-up for glazed leaves, and whether frames travel assembled or flat
- Pallet or crate marking that matches the door tags on the schedule
- Delivery sequence by floor or zone, so openings are ready when each lot lands
- Storage conditions on site and who inspects each crate at receipt
Our logistics and door-to-door delivery service covers freight booking, customs paperwork, container loading plans and shipment tracking. Because import terms, duties and delivery scope differ by destination and by consignment, the agreed Incoterms and delivery address should appear on the submittal cover sheet so both sides are pricing the same arrangement.
7. Installation Method and After-Sales Terms
Close the package with the method, not just the product: fixing method into the surrounding wall build-up, packing and shim arrangement, sealant type at the frame line, ironmongery adjustment sequence, and the snag list format used at handover. Then state what happens afterwards — warranty scope, what is excluded, and how replacement leaves or hardware are ordered later. Our installation and after-sales support page describes on-site installation, inspection and snagging, warranty coverage and spare parts; the terms that apply to your project belong in the submittal as confirmed figures rather than a general promise.
What To Check Before You Submit
| Item | Confirmed by | Status |
|---|---|---|
| Site-measured opening sizes at three heights per opening | Site contractor / our technical team | To be signed before order confirmation |
| Leaf size, frame section and glazing-bar layout on a scaled drawing | Designer of record | Shop drawing approval |
| Finish sample code and glazing sample | Client or interior designer | Physical sample signed and retained |
| Swing, hand, active leaf and hardware set | Hardware supplier and door manufacturer | Cross-checked against the schedule |
| Incoterms, delivery address and delivery sequence | Procurement and logistics | Written on the cover sheet |
| Warranty scope, exclusions and spare-part route | Purchaser and supplier | Recorded in the approval record |
One practical habit saves rework: circulate the dimensional sheet first and hold everything else until it is signed. Finish, glazing and hardware decisions all assume an opening that has been measured and accepted.
Send Us Your Door Schedule
If you are preparing a submittal for French double doors or another opening in a villa, hotel or office fit-out, send the door schedule and the relevant elevations to SANTERSON. We are a China-based furniture and building materials manufacturer working on custom and OEM orders, and we return marked-up shop drawings, finish samples and a specification sheet you can put straight into your submittal package.