A materials schedule is the document that keeps a fit-out honest. It records, line by line, what each finish actually is, where it appears, who supplies it and what still has to be confirmed before production starts. When solid color acrylic cabinets enter that schedule, they rarely cause problems because the material is difficult to specify - they cause problems because a single cabinet line has to carry finish code, substrate, hardware, tolerance and lead-time information at the same moment as every other finish in the building. This article walks through how to write that line properly and how to keep it aligned with the rest of the package.
Why a cabinet line belongs in the schedule, not in a drawing note
On many residential and small hospitality packages, joinery is left to a drawing annotation: "acrylic cabinetry, colour to architect's selection". That wording survives tender and then collapses at shop-drawing stage, because three different parties read it three different ways. The designer assumes a specific sheen level. The contractor assumes an availability date. The manufacturer assumes the substrate and edge treatment are already agreed.
A schedule line forces those assumptions into the open. Once the cabinet is written as a row with fields - location, finish code, door style, substrate, edge banding, hardware, lead time, approval status - the gaps become visible while they are still cheap to close. That matters most on whole-project packages, where kitchen cabinetry shares the same procurement window as wardrobes, wall panelling, doors, flooring and bathroom fixtures. A cabinet that is approved two weeks late holds up site measurement, then delivery, then installation of everything that abuts it.
SANTERSON works as a furniture and building materials manufacturer and one-stop supplier, supplying cabinetry alongside the other finishes in the same package. That changes what a good schedule looks like: instead of twelve separate supplier sheets, you write one schedule that a single procurement team can price, coordinate and deliver together.
What a complete cabinet line has to carry
Use the same field structure for joinery as you already use for stone, tile and metalwork. A short checklist of what each row needs:
- Location and unit type. Not "kitchen", but which kitchen, which elevation, and whether the run includes tall units, an island or integrated appliance housings.
- Finish family and finish code. Acrylic is a family; the code is the specific colour and sheen. Write both, so a substitution can never be argued as "the same acrylic".
- Door style and construction. Slab, handleless, framed or integrated-appliance front, with the rail and stile arrangement where it applies.
- Substrate and edge treatment. Panel type, thickness and whether edges are wrapped, mitred or lipped. This is where visual matching between units usually fails.
- Hardware. Hinges, runners, handles or integrated profiles, listed separately so they can be approved on their own cycle.
- Dimension basis. Whether the sizes are design-stage setouts or site-verified. Made-to-measure joinery should never be released for production off unverified dimensions.
- Approval status and date. Sample seen, sample approved, shop drawings issued, released for production.
The Solid Color Acrylic Cabinets line in our catalogue is specified on exactly that basis: made-to-measure sizing, material and finish options, and a layout tailored to the project. The schedule row is what converts those options into a fixed order.
Writing the finish column without creating an argument later
Solid colour acrylic covers a wide visual range, and the differences are not obvious on a specification sheet - they are obvious on a completed wall in daylight. Handle the finish column in three steps.
1. Name the sheen before the colour
Two identical colours at different sheen levels read as two completely different kitchens. Decide first whether the run is high gloss or matte, then choose the colour. Within the same acrylic collection you can specify high gloss acrylic cabinets for a feature run and matte acrylic cabinets elsewhere; writing the sheen in the schedule keeps the two from being quoted as interchangeable.
2. Record what you actually approved
Write the sample reference, its physical size and who signed it off. A colour chip the size of a business card tells you almost nothing about how a full-height door will behave under downlights or near a window. Where the schedule records "sample approved" with no reference, that field is empty in practice.
3. Keep related finishes in one place
A kitchen rarely stands alone. Benchtops, splashbacks, flooring and adjacent wardrobe doors all sit against the cabinet fronts. Where wardrobes are also acrylic, list them next to the kitchen rows so colour and sheen can be compared side by side - for example white acrylic wardrobes meeting an off-white kitchen run. Two approved samples that looked acceptable separately can clash badly once installed.
A worked example: one apartment, one schedule
Consider a three-bedroom apartment where the kitchen, laundry and bedroom storage are all acrylic-fronted. Written as a schedule rather than as drawing notes, the joinery section might read:
| Ref | Location / unit | Finish entry as written in the schedule | Status to be closed before production |
|---|---|---|---|
| K-01 | Kitchen perimeter, tall units and island | Solid colour acrylic, slab door, sheen and colour code recorded with sample reference; substrate and edge treatment stated; handleless profile listed as separate hardware line | Site-verified dimensions; hardware approved; shop drawings signed |
| K-02 | Integrated appliance fronts | Same finish family and code as K-01, edge detail noted for continuity with the adjacent tall run | Appliance models fixed; door fixings confirmed with appliance supplier |
| L-01 | Laundry cabinetry | Same colour family, sheen recorded separately where the laundry is not in the client's sightline | Wet-area exposure and plinth detail agreed |
| B-01 | Bedroom wardrobes | Acrylic fronts listed with their own code, so a matching colour can be compared against K-01 rather than assumed | Door configuration (hinged or sliding) fixed; sample comparison signed |
Four rows, one format. Anyone reading the schedule - quantity surveyor, site supervisor, factory - sees the same information and the same open items.
Where whole-project packages usually break down
Finishes approved in isolation. Cabinet fronts signed off on a desk, then compared with flooring and stone once they are on site. Put every acrylic row beside the rows for the finishes it touches, and review them as groups.
Hardware treated as part of the door. Hinges and runners have their own supply cycle and their own load ratings. Split them into separate lines with separate status columns.
Dimension basis left blank. Design-stage setouts and site-verified dimensions are not the same thing. A made-to-measure order released on the wrong one is the most expensive avoidable error in joinery procurement.
Substitutions approved by email. If a finish or hardware item changes, the schedule row changes with it, dated and initialled. Otherwise the shop drawings and the site reality diverge and nobody can say when.
High glossMatteMetallicPatternedTwo toneWithin one acrylic collection, these families can be mixed across a project. The schedule is what keeps the mix deliberate instead of accidental.
Keeping cabinetry in step with the rest of the package
Joinery sits on the critical path because it depends on site measurement and everything else depends on it. Where one supplier covers cabinetry, wardrobes, doors, panelling, flooring and other fit-out items, coordination collapses into a single production plan rather than a set of parallel promises. SANTERSON's custom and OEM service covers bespoke finishes, textures and dimensions to project drawings, which is what makes one schedule workable across several product families instead of several separate documents.
On the delivery side, logistics and door-to-door delivery covers freight, packaging, container loading and customs documentation, so the schedule's lead-time column can be filled with real shipping information rather than estimates. Installation and after-sales support close out the snags that joinery always generates on site.
Before you send the schedule for pricing
- Every acrylic row names both the finish family and the specific colour and sheen code.
- Sample references, sizes and approval dates are recorded, not implied.
- Substrate, thickness and edge treatment appear on each cabinet line.
- Hardware sits on its own lines with its own status.
- Dimension basis is stated, and no made-to-measure unit is released off unverified dimensions.
- Adjoining finishes - stone, flooring, wardrobe fronts - are grouped for side-by-side review.
- Every substitution has a dated entry in the schedule itself.
If you are assembling a materials schedule that carries cabinetry alongside other fit-out products, send us the schedule and the drawings. We will price the joinery against it, flag any field that is not yet specifiable and confirm dimensions and selected specifications for each project before production starts.