A wall hung toilet is one of the smallest items on a fit-out bill of quantities and one of the easiest to get wrong. The bowl arrives on a container, the concealed frame does not, and the rough-in dimension on the drawings does not match the outlet on the carton. Below is the practical sequence we follow when an overseas buyer orders the Wall Hung Toilet 1038W, Rimless Ceramic Wall Mounted WC for Modern Bathroom as a project order and has it shipped internationally.

Why a Project Order Behaves Differently From a Sample Order

A single unit is a parcel. A project order of the 1038W is a set of interdependent decisions: quantity per bathroom type, trap orientation, carton strength for ocean freight, and a delivery address that may be a hotel tower under construction rather than a warehouse. The commercial terms, the packing standard and the paperwork all change once the order is destined for a building site instead of a showroom.

SANTERSON works as a China-based manufacturer and one-stop supplier of furniture and building materials, so bathroom ceramics usually travel alongside other fixtures from the same project package. That consolidation is where most of the savings appear, provided the schedule for each trade line up. Our Furniture Logistics and Door-to-door Delivery service covers freight forwarding by sea, air and rail, customs documentation, container loading and tracking to the site.

Step 1: Confirm the Technical Data Before You Confirm the Quantity

The 1038W is a wall-hung vitreous ceramic WC with a seamless glaze, designed for a concealed tank and a compact footprint, so it suits guest bathrooms and en-suites where the floor is left clear for cleaning. The published page describes an 180 mm P-trap wall drainage arrangement. Treat that number as the first thing to verify against your drawings, because a wall-hung WC cannot be installed on a floor outlet without changing either the product or the waste run.

What we ask a buyer to sign off before production: trap type and rough-in dimension; concealed frame brand and carrier set height that will be used on site; rimless bowl and actuator plate finish; number of pieces per bathroom type; and whether spare units are required for handover maintenance.

If your project uses a floor outlet, the Two Piece Washdown Toilet 1038A, Dual S Trap & P Trap Ceramic WC Toilet for Hotel Bathroom belongs to the same design family and offers both a wall outlet and a floor outlet option, which keeps the visual language consistent across bathrooms with different drainage. We can quote both models in one order so the two types are produced together.

Step 2: Lock Quantity, Batches and Delivery Points

Ceramic ware is usually ordered in one production batch for a single building. Splitting an order across batches is legitimate when phases of a hotel or apartment project are handed over at different times, but it has consequences you should decide on knowingly:

  • Glaze tone and hardware finish can vary slightly between production runs, so phased projects need approved sealed samples kept at the factory for comparison.
  • A smaller second batch may not fill a container on its own, which changes the freight cost per piece more than the unit price does.
  • Delivery points matter. A central warehouse is straightforward; a site with limited storage and a fixed lift schedule needs staged releases instead of one large shipment.

Tell us the room-by-room take-off, not just a total. We map quantities to bathroom types so the spare allowance for future maintenance is deliberate rather than guesswork.

Step 3: Choose the Packing Standard and the Loading Plan

Breakage on ceramics is almost always a packing and handling question, not a manufacturing one. For project orders we use reinforced cartons with moulded corner protection and edge protectors, then stack to a loading plan that keeps heavy items low and avoids point loads against the container walls.

DecisionWhat it affectsTypical buyer choice on project orders
Packing grade (standard export carton versus reinforced crate-style packing)Breakage rate, cubic metres per container, handling time on siteReinforced packing for multi-model mixed containers and long sea legs
Mixed container versus dedicated containerConsolidation savings versus unloading sequenceMixed, with pallets labelled by bathroom type or floor
Cargo insuranceWho absorbs loss in transitInsured shipment on ocean freight for ceramic lines
Incoterms and delivery pointWho handles customs, duties and last-mile haulageDoor-to-door when the buyer has no local clearing agent

We provide commercial invoices, packing lists, certificates of origin and the other import paperwork your clearing agent requires. Import duties, taxes and any permit obligations remain a matter for your customs broker and your local regulations; we supply documents, not compliance advice.

Step 4: Match the Shipping Mode to the Site Programme

Ocean freight is the default for project quantities. Air freight only makes sense for a short top-up batch, replacement units after snagging, or an early sample set that the design team must approve before production starts. Rail sits between the two on some corridors.

  • Work backwards from installation, not from order date. Wall-hung WCs are fitted after the concealed frame, wall lining and tiling setting-out are complete, so the delivery window should sit just before that trade sequence, not at the start of the job.
  • Allow for storage. A site without dry storage needs a shorter lead time between arrival and installation; a site with a laydown area can absorb an early arrival.
  • Sequence the container. Bathroom ceramics that arrive after the joinery and before the final fix trade are useful; the same cartons arriving after the painter starts work create double handling.

Step 5: Consolidate With the Rest of the Bathroom Package

Ordering the bowl alone usually means sourcing the matching basin, shower and accessories from someone else, and that is where schedules fracture. The same project container can carry the rest of the suite:

One purchase order, one production schedule, one container and one set of documents is the argument for consolidating bathroom ceramics with the joinery, lighting and flooring lines from the same project. It also means a single point of contact when something on the packing list does not match what arrived.

Step 6: Receive, Inspect and Hand Over

Inspection works best when it happens while the cartons are still at the delivery point and a claim is possible:

  • Count cartons against the packing list before signing, and photograph any damaged carton before opening it.
  • Open a representative sample of cartons from different pallets, not all from one stack, and check glaze finish and included fittings.
  • Keep the sealed spare units for handover; they are what makes a replacement years later an exact match rather than a compromise.

Our Furniture Installation and After-sales Support service covers on-site fitting support, inspection with snag lists, spare parts and replacement for damaged units. Warranty terms, response times and what is excluded are set out per project in writing before shipment, so ask for them rather than assuming a standard.

Common Failures We See on International WC Orders

  • Rough-in mismatch discovered after tiling. The wall outlet is set out from the finished face of the tile, not the bare blockwork. Confirm the dimension with the completed finish allowance before production.
  • Frame and bowl ordered separately. The concealed carrier dictates mounting height and actuator position; mixing an uncoordinated frame with a bowl bought elsewhere is the most frequent cause of a delayed bathroom sign-off.
  • No spare allowance. Hotels and apartment blocks need spares for maintenance. Order them with the main batch, when the production run is open.
  • Delivered to a site that cannot receive it. Book the delivery window against site access, lift availability and storage, not just against the vessel arrival date.

A Short Checklist for Buyers

  • Signed-off technical sheet: trap type, rough-in dimension, overall size, finish, actuator plate.
  • Concealed frame decision documented and coordinated with the bowl order.
  • Room-by-room quantity plus a stated spare allowance.
  • Packing grade and container loading plan agreed in writing.
  • Incoterms, delivery point, insurance and clearing responsibility named in one place.
  • Delivery window matched to the installation sequence on site.
  • Inspection protocol agreed before the truck arrives.

Frequently Asked Questions

Can you ship a mixed container of bathroom ceramics and other fixtures?

Yes. Mixed containers are normal on project work, with pallets labelled by floor or bathroom type so the unloading order matches the installation programme.

What if a unit arrives damaged?

Photograph the carton and the item at the delivery point, note it on the delivery paperwork, and send us the photos with the packing-list line. We arrange replacement units for damaged pieces under the terms agreed for that order.

Can you supply the 1038W together with matching basins and showers?

Yes, from the same catalogue. See Turnkey Interior Project Solutions for how a full package is coordinated from design through to handover.

Start With the Technical Sheet, Not the Price Sheet

Send us the room-by-room take-off and your drainage setting-out, and we will return a quotation for the 1038W with the packing standard, loading plan and document set attached, so the commercial decision and the logistics decision are made at the same time.