Procurement Guide / Modular Living Systems
A floating modular living wall is one of the easiest built-in elements to get wrong on a residential project, because it looks simple on a drawing and carries a lot of hidden decisions underneath. When we receive an enquiry about Santerson Floating Modular Systems, the enquiries that move fastest are the ones that arrive as a proper submittal package rather than a single render. This guide sets out what we need in that package, why each item matters on site, and what you can expect back from our team.
What a Submittal Actually Does for Your Project
A product submittal is the document set a contractor, designer or developer sends to the manufacturer so that a quotation, a shop drawing and finally production all start from the same information. For floating modular systems it is worth more than for a loose furniture item, because these units are made to measure, fixed to the wall, and usually coordinated with lighting, joinery and floor finishes around them.
If any of that information arrives late, the practical result is not a delayed email. It is a re-cut panel, a returned crate, or a shelf that will not line up with the skirting already installed. Our custom furniture design and prototyping service begins once the specification is settled, so the quality of your submittal directly sets how quickly the project reaches production.
The Seven Items We Expect in a Complete Package
1. Room elevation and overall envelope dimensions
Send the wall elevation with the total width and height of the run, plus the ceiling height where the unit stops short of the slab. Give dimensions in millimetres and state whether the figures are finished-face or structural. A floating system has to clear skirting boards, cornices, architraves, radiator positions and any recessed niche, so mark those obstructions on the drawing rather than describing them in an email.
2. Fixing substrate and wall construction
This is the item most often missing. Tell us what is behind the finish: solid masonry, blockwork with a cavity, timber stud with plasterboard, steel stud, or an existing joinery panel. A floating unit carries its load through a hidden batten and fixing system, and the correct anchor type depends entirely on that substrate. Where you are not yet sure, say so and give the wall build-up from the architectural specification; we will flag it as a site verification item instead of guessing.
3. Layout intent and module mix
State what the unit has to hold: books, display objects, tableware, media equipment, or a mix. Open display niches behave differently from closed compartments, and a run that mixes both needs its proportions decided before shop drawings. If you are weighing a floating arrangement against a full-height alternative such as Santerson Floor to Ceiling Modular Systems, send both options and we will price them side by side so the comparison is real rather than estimated.
4. Material and finish schedule
Name the substrate and the surface you want, and identify any existing item the new work has to match — a door veneer, a wardrobe lacquer, a floor. Our custom furniture materials and finishes options cover wood, metals, engineered stone and laminates, but a physical reference is always safer than a colour name. Send the make and model of an existing laminate or paint system where one exists, and tell us the sheen level you expect.
5. Lighting and services requirements
If the design calls for shelf lighting, specify whether you want fixtures integrated into the carcass or a surface-mounted alternative, and confirm where the driver will sit and who is pulling the cable to that point. Integrated lighting needs its wiring route agreed at shop-drawing stage, because cabling has to be concealed inside the panel build-up. If there is no electrical provision yet, mark it as pending rather than leaving it out.
6. Quantities, room schedule and delivery address
Give the number of linear metres or units per room, and list rooms separately when finishes differ. Include the site delivery address and, for a multi-unit development, the floor and unit numbers. This is also where one-stop furniture and building materials project procurement pays off: if the same package covers wardrobes, vanities, doors or panelling for the same floors, we can consolidate them into one production and shipment plan instead of several.
7. Programme and phasing
Tell us when the units are needed on site and which rooms come first. Built-in joinery is normally installed after wet trades and floor finishes, so a realistic install window lets us sequence production rather than default to one large batch.
Submittal Checklist at a Glance
| Item | What good looks like | Risk if omitted |
|---|---|---|
| Elevation drawing | Annotated widths and heights in millimetres, obstructions marked | Units clash with skirting, cornices or niches |
| Wall build-up | Substrate material and board thickness stated | Wrong fixing detail; load capacity unconfirmed |
| Module mix | Open and closed compartments listed per run | Storage does not match how the room is used |
| Finish reference | Physical sample, or make and model of existing finish | Tone or sheen mismatch against adjacent joinery |
| Lighting note | Fixture type, driver location, electrical responsibility | Cabling cannot be concealed later |
| Quantities and address | Per-room schedule with unit numbers | Partial shipment, install delay on site |
| Programme | Required on-site date and room sequence | Joinery arrives before the room is ready |
What Comes Back to You From Santerson
Once the package is complete, our reply follows the same order your design team works in. First a specification review, where we mark anything that needs a site check — usually substrate, level tolerance or an electrical route. Then a quotation with the material and finish breakdown stated rather than bundled into one line. After that comes production coordination under our interior design services, which cover space planning, furniture layouts and 3D renderings alongside drawing and production coordination.
For packages that extend beyond one product family, we also handle furniture logistics and door-to-door delivery, including freight by sea, air or rail, customs paperwork and container loading planning. Installation support and after-sales service are arranged through the same project contact, so the handover is not left to whoever happens to be on site that week.
Three Gaps That Slow Approvals Down
Rendering without dimensions. A mood image tells us the intent but not the envelope. Approvals stall while someone redraws it. Send the dimensioned elevation even when it is rough.
Finish named in words only. "Matt oak" means something different to every factory. A sample, a photograph of the installed reference, or a manufacturer code settles it in one round instead of three.
Assumed wall condition. Where a renovation has opened up unknown structure behind the plasterboard, ask for a site check before we detail the fixing. It is cheaper to confirm a substrate than to re-manufacture a panel that cannot be anchored.
Putting It Together
A strong submittal for Santerson Floating Modular Systems answers six questions before we ask them: where it is going, what is behind the wall, what it must hold, what it has to match, whether it carries light, and when it must arrive. Those six are also the six that decide price, so a complete package protects both the programme and the budget.
Send your drawings and finish references to our project team and we will return a reviewed specification with the site verification items clearly listed.