A glass-front bookshelf looks finished in a rendering long before it is finished on site. Glazing shows every misaligned shelf, every uneven wall, and every case that was set out of plumb. That is exactly why an installation plan for Santerson Glass Front Bookshelves needs to be written before production starts, not handed over with the crates. The following checklist covers what a working plan should contain, from site measurement through to final inspection.
1. Measured drawings of the receiving wall, not the design intent
Glass-front cases are usually specified as made-to-measure units, so the wall condition is part of the product decision. The plan should record what the site actually presents:
- Finished floor and finished ceiling levels, plus the clear height between them at each end of the run.
- Wall plumb and flatness readings along the full length of the intended run — glass fronts reveal a bowing wall immediately.
- Positions of skirting, architraves, cornices, switches, sockets, air diffusers and light switches that the case has to clear or scribe around.
- Whether the substrate can take fixings: stud positions, masonry, plasterboard, or a cavity that needs noggins or an intermittent batten frame.
- Existing doors, returns and corners that affect how a case is carried in and assembled in place.
Send these readings back to the factory with the order. Where a run will be built from several cases, note which joints are butted, which are scribed, and where a filler panel or concealed scribe is expected. This is the difference between a straight glazed front and one that steps at every joint.
2. A case-by-case schedule with dimensions and finish codes
Every unit in the plan should have its own line, keyed to a drawing number so the site team can match crate labels to positions without guessing.
| Field in the schedule | Why it matters for glass fronts |
|---|---|
| Case tag and wall position on the plan | Crates arrive mixed; the tag tells the fitter where each case goes before it is unwrapped. |
| Width, height, depth at finished condition | Confirms clearance for handles, doors and any adjacent joinery before fixing starts. |
| Body material, door style and finish code | Finish samples are approved against a code, so replacements or additions match later. |
| Glass type, colour and glazing side | Tinted, ribbed or clear glass reads differently against the interior of the case; the plan should say which face is visible. |
| Shelf count, spacing and fixed versus adjustable | Books have predictable heights; specify shelf pitch for the collection being stored, not a generic grid. |
| Hardware: hinges, handles, locks, soft close | Hardware must be ordered with the case; retrofitted fittings mark a glazed door. |
| Integrated lighting and cable route | Recessed or surface fittings need a cable path and a driver location decided before the case is fixed to the wall. |
If part of the wall stays open rather than glazed, keep those units in the same schedule. Mixing open bookshelf bays with glazed ones is common, and the two need consistent shelf lines and reveal depths.
3. Fixing method and interface details
The plan should state how the units are restrained, not leave it to the fitter's habit. Include:
- The fixing substrate agreed on site: timber noggin, steel frame, or a specific anchor type for masonry.
- Fixing centres and the position of battens behind the case, shown on the drawing so they can be installed before finishes close up.
- Whether cases are joined to each other first and then hung as a run, or fixed individually — this changes the sequence of the whole job.
- Tolerance allowance at ceiling and floor, and how gaps are closed: scribed panel, filler, or shadow gap detail.
- Anti-tip restraint requirements for tall glazed units, and where blocking is needed to receive it.
- Protection strategy for glass during the rest of the works, especially where painting, flooring or electrical trades follow.
For full-height runs, decide at planning stage whether the wall-mounted shelving and closed units in the same wall are installed before or after the glazed cases. Sequencing wrong means either a protected glass front on site for weeks, or a chipped edge at handover.
4. Coordination with the other trades on that wall
Built-in shelving rarely sits alone. The plan should show, on one drawing, where it meets:
- Electrical: sockets, switches and reading lights inside or beside the case, plus driver access for any integrated lighting.
- Lighting design: whether display niches are lit from the case or from the ceiling, and who supplies the fitting.
- Joinery and wall panelling: reveal lines, matching veneer or lacquer edges, and where a concealed door or panel interrupts the run.
- Floor finishes: whether the case sits on the finished floor with a scribed base, or is set into the flooring detail.
- Painting and decorating: where the paint stop is, so no cutting-in is attempted against glazed glass.
SANTERSON's project service covers drawings and production coordination with on-site guidance, so this interface drawing is worth requesting rather than reconstructing locally. It is also the document to circulate to the electrical and flooring contractors before their own shop drawings are issued.
5. Logistics assumptions that affect the install date
A glass-front case is a freight problem as much as a joinery problem. The plan should record:
- Packaging and crate labelling, with tags matching the schedule, and how many crates arrive in one delivery.
- The delivery route on site: door widths, lift dimensions, stair turns and corridor clearances for full-height cases.
- Storage location — dry, level, off the floor, away from trade traffic — and who signs for glass condition at receipt.
- Inspection of glazing at unpacking, with damage reported immediately rather than after installation.
Where a project needs the rest of the wall furnished as well, ordering the glazed cases together with related built-in furniture from the same supplier keeps shelf lines, finishes and delivery windows on one schedule. Modular bookshelf systems and closed bookshelves in the same collection are typically specified to the same finish codes, which is what makes a mixed open-and-closed wall read as one piece of joinery.
6. Inspection and handover items
Close the plan with a snag list the client can actually use:
- Case plumb, level and line along the full run; joints flush with no visible step.
- Glass clean, free of chips and scratches, seated correctly in its rebate or fitting.
- Doors aligned with even reveals; hinges and soft-close hardware working; locks keyed as scheduled.
- Shelves set to the specified pitch, with adjustable pins engaged in a bearing surface.
- Lighting on all fittings, drivers accessible for service, no visible cable or patch panel.
- Scribed and filler panels matched in colour and grain direction.
- Anti-tip restraint installed and recorded on the as-built sheet.
- Spare shelf pins, hinges and one glazing bead handed over with the maintenance manual.
Warranty terms, spare-part supply and response times should be written into the plan from the supplier's own stated conditions for that order. Confirm them in writing for your project rather than assuming a standard period applies to glazed components.
Before you issue the plan: three checks
- Can a fitter place every case from the drawings alone? If not, add tags, levels and fixing centres.
- Is every interface shown with a named trade? Unassigned interfaces are what get discovered on site.
- Does the schedule match the approved quotation line by line? Finish codes, glass type and hardware should read identically in both documents.
A plan that answers those three questions protects the glass, the finish and the programme. One that does not will be paid for in rework on a visible wall.