Floating modular systems look simple on a mood board and complicated on site. Because every module is made to measure, the wall fixing, the finish delivery and the trades' programme all have to agree before production starts. This guide walks through how we plan delivery and installation for Santerson Floating Modular Systems on villa and residential projects, and what we need from the site team at each stage.

Why floating modular systems are scheduled differently

A floating modular living system is a wall-mounted storage and display composition: carcasses, shelves, closed units and often integrated lighting, sized to the room rather than bought off a shelf. Our product listings for these systems list made-to-measure dimensions with selectable materials and finishes, which means the order only becomes fixed once the layout, sizes and finish samples are signed off.

That single fact drives the whole programme. Wall-mounted components rely on the substrate behind them, so the wall build-up, embedded services and any reinforcement must be complete before our crates arrive. If the plasterboard is still open or the electrician has not pulled the feeds for the lighting, installation slips even though the units themselves have landed.

Stage 1: lock the specification before production

We work from your project brief and drawings. The items we need confirmed in writing are:

  • Room-by-room layout of each composition, with heights, widths and module splits taken from the finished floor level.
  • Wall construction and load path for every fixing line — solid substrate, timber or steel studs with noggins, or a backing frame to be supplied on site.
  • Finish selection: material, colour and sheen, approved against a physical sample rather than a screen image.
  • Electrical provision for integrated lighting and media positions, including switch locations and access points for drivers.
  • Clearances for doors, skirting, radiators, curtains and any adjacent joinery.

Where a project mixes systems, we group them on one production order so they travel together. Projects that combine floating units with Santerson Floor to Ceiling Modular Systems or Santerson Floating Modular Shelves are usually sequenced so the freestanding and full-height work is installed first, leaving a clean, protected wall face for the floating elements.

Stage 2: match production to your site programme

Our service covers design consultation and space planning, material selection and product specification, manufacturing with quality control, project management and site coordination, then final installation and handover. For a modular package we normally set the production start after the joinery and wall set-out drawings are returned approved, so the factory is building to the real site dimensions and not to a design-stage drawing that will move.

Practical rule of thumb: schedule the specification sign-off so production finishes after the wet trades and wall linings are complete, but before flooring protection goes down in the rooms where the crates need to pass. We confirm dates against your programme rather than quoting a generic lead time, because modular work is made to order.

Stage 3: freight, packaging and container loading

Modular units are panel work, so packaging and handling decide how much of the finish survives the journey. Our logistics service covers sea, air and rail freight forwarding, customs paperwork such as commercial invoices, packing lists and certificates of origin, packaging and container loading plans, shipment tracking and door-to-door delivery.

Delivery decisionWhat to settle before booking
Consolidated or split shipmentWhether the modular package ships with cabinetry, wardrobes and other joinery, or arrives separately for a later phase.
Delivery address and accessTruck size, unloading area, lift capacity for upper floors, and whether crates can be stored inside rather than outside.
Incoterms and import stepsWho clears customs, who pays duty, and who arranges the final leg to site. Confirm these per project in writing.
Inspection windowPhotograph and check every carton against the packing list on arrival, and report any damage the same day with photos.

Keep the packing list on site. Each module is labelled to a room and elevation, which is what lets the installers lay out the components in sequence instead of opening everything at once.

Stage 4: site preparation checklist

Before our installation team or your fitters start:

  • Walls finished, flat and dry, with the setting-out lines marked on site.
  • Reinforcement or backing frames fixed at the fixing heights shown on the drawings.
  • Electrical feeds tested, with drivers and dimmers accessible behind removable panels.
  • Floor levels confirmed and recorded, since floating modules are dimensioned from finished floor level.
  • A clean, dry staging area of roughly one to two rooms' worth of space for unpacking.

If any of these are outstanding, tell us before the delivery date is fixed. Rescheduling a crate that has already cleared customs costs far more than moving a production date.

Stage 5: installation sequence and handover

Our installation and after-sales service covers on-site installation, inspection and snag resolution, warranty coverage, spare parts and replacement, and ongoing maintenance. For a floating system the typical sequence is:

  • Lay out all components against the packing list and check for transit damage.
  • Mark and drill the fixing line, confirming stud or backing positions first.
  • Fix the primary carcasses, checking level and reveal at every step.
  • Add shelves, closed units and doors, then adjust hinges and soft-close hardware.
  • Wire the integrated lighting, fit diffusers, and test every circuit before closing panels.
  • Walk the installation with the client or site supervisor and record snags on a single list.

Handover is complete when the snag list is closed and the care instructions for the selected finish have been passed to whoever maintains the property. On multi-unit residential work we repeat this room by room, so sign-off does not wait for the last apartment.

Common causes of delay, and how to avoid them

  • Late finish changes. A finish change after production starts usually means a new batch. Approve finishes from physical samples at the specification stage.
  • Unconfirmed wall build-up. If the substrate is decided late, fixing details have to be re-engineered and extra hardware ships separately.
  • Storage on site. Panels left in a damp or unventilated space swell at the edges. Store flat, indoors and wrapped until installation.
  • Trade clashes. Electricians, floorers and installers in the same room on the same day create damage. Book the modular installation as its own window.

Planning a project with us

As a China-based furniture and building materials manufacturer working on villa, hospitality and office projects, we supply the modular systems together with the cabinetry, wardrobes, doors, flooring and lighting that surround them, so one team coordinates the package from drawings to handover. Send us your drawings, room list and programme dates and we will return a specification review with the fixing details, packaging plan and delivery sequence for your site.