A swim spa that measures close to twelve metres long is not a product you drop into a garden and switch on. It arrives in sections, needs a slab that can carry a loaded shell, and it pulls power, drains water and moves people through a site that may already be finished. Before the first truck is booked, the Outdoor Swim Spa WS-S12 needs the same kind of drawing pack a bathroom fit-out would get: measured site data, an equipment schedule, services routed to the right place, and a named sequence for delivery, installation and handover. The plan below lists what we ask project teams to put in writing before production starts.

1. Site data, not assumptions

Send us the survey information first, because it decides whether a spa of this size can physically reach the position on your layout. We need:

  • The clear access route from the delivery point to the final position: gate widths, turning radii, overhead cables, tree canopy and any step or slope along the way.
  • The finished ground level and the level of the surrounding paving, so we can set the shell height against your deck instead of guessing it later.
  • A slab or plinth detail showing reinforcement and the load it is designed to carry once the shell is full, with the wet area treated as a permanent load rather than a temporary one.
  • Distance from the spa to the nearest power intake, drainage connection and property boundary, since these set cable runs, pipe falls and how much plant space you keep behind the unit.

Where the site is a completed villa or a resort terrace with limited working room, tell us early. It usually changes the delivery method and the order of the installation steps, not the product itself.

2. Configuration sheet signed off before production

The catalog specification for this model is a starting point, not an order. Confirm every line in writing on the configuration sheet: shell colour, control system, number and type of pumps, jet layout, lighting, ozone or optional UV sterilisation, heat pump output, insulation package, sand filtration where specified, and steps. The same rule applies if you choose the variant with a swim training system, Outdoor Swim Spa WS-S12-T; that option changes the plant room layout and the electrical load, so it has to be fixed before the shell is built.

Catalog figures for WS-S12, for cross-checking against your configuration sheet:

Overall size 11740 × 2200 × 1470 mm; control system 1 set; water pump 2 pcs; filter pump 1 pc; jet total 73 pcs; LED lights 1 with 50 small LED lights; total power 7.65 kW.

Treat these as catalog values. Your signed configuration is the document the installer works from, and any difference between the two should be resolved on paper before shipment.

3. Electrical scope drawn out in advance

A 7.65 kW total power figure is enough to tell you that a standard outdoor socket will not do, but it is not the whole answer. Your electrical consultant should produce a single-line diagram showing the supply capacity at the intake, the dedicated circuit and its protection, the location of the isolator, cable routing and containment, bonding around the wet zone, and where the control system sits so it stays reachable for operation and service. If a heat pump is on your option list, its draw goes on the same drawing, together with any future circuit you want left spare.

Local electrical rules differ by country and by municipality. We supply the equipment schedule and connection requirements; the local licensed contractor signs off compliance for the installation. Put that split in the contract so nobody assumes someone else covered it.

4. Civil and waterproofing details

The civil package should show the slab edge, the recess or plinth if the spa is partly sunk, the drainage channel around the shell, the fall of the surrounding paving away from the unit, and the access provision for the plant components. If the spa sits on an upper terrace or a balcony structure, the structural engineer's note confirming the imposed load belongs in this section as well.

Decide now how the site will be washed down. A swim spa at poolside generates wet traffic, so paving slip rating and drainage capacity are decisions for the design stage, not snag lists at handover.

5. Delivery, access and lifting sequence

Long sections and a wide shell need a written arrival plan: delivery date window, vehicle size, unloading method, crane or forklift hire if the route cannot take a manual carry, protection of finished floors and paving, and the crew needed to position the shell in one move. We arrange freight forwarding, packaging and container loading as part of logistics and door-to-door delivery; your side confirms site access on the agreed day. When the two schedules are not aligned, the cost usually lands on the project, so we recommend naming one coordinator for both halves.

6. Commissioning and handover documents

Installation is finished when the record set is complete. We suggest your plan require:

  • A filled commissioning sheet: fill volume reached, jet and pump operation checked, control system parameters recorded, lighting and ozone function tested.
  • Water treatment handover: which dosing or sterilisation option was supplied, and the routine your maintenance team will follow.
  • Warranty terms in writing, with what is covered, what site work is excluded, and how a claim is raised.
  • Spare parts list for consumables such as filters and seals, plus contact details for support.
  • A signed snag sheet closing out any items found during inspection.

Our installation and after-sales support covers on-site guidance, inspection and follow-up, and it fits into this sequence rather than replacing the local trades who pour the slab and terminate the power.

Where the swim spa sits in a wider project package

On most villa and hospitality jobs we supply, the pool deck is one line among many: outdoor dining sets, loungers, pergolas, paving, wall panels, bathroom fixtures and lighting all move on the same programme. Coordinating them together avoids the classic failure of a spa delivered before the paving team arrives, or a heat pump installed after the terrace cladding is closed in. If you are assembling several of these scopes at once, our turnkey interior project solutions start from a single drawing set and one production schedule.

Space on site is often the deciding factor. Where the twelve-metre footprint will not fit, we produce customizable shape outdoor spas in square, round, oval and curved layouts, so the water feature follows the plan instead of the other way around.

Send us your site measurements, a photo of the access route and your preferred configuration list. We will return an equipment schedule with the connection requirements for that configuration, so your civil and electrical consultants can price their work against real numbers. Contact SANTERSON through the contact page to start the pre-installation review.