A set of minimalist simple kitchen cabinets looks effortless on site. Getting it there is anything but: cabinetry is a made-to-order, oversized interior fixture that has to survive ocean freight, customs clearance and an unloading point that may be a tenth-floor apartment or a hillside villa. This guide walks through the sequence we follow on project orders, from the drawing stage to the container arriving at your door.

Why a Cabinet Order Is Not Ordinary Cargo

Cabinetry behaves differently from loose furniture in three ways that change the whole shipping plan. First, every unit is built to your dimensions and finish, so a measurement error cannot be corrected on site — it has to be remanufactured and shipped again. Second, panels are large and flat with edges that chip easily, which dictates how they are packed and stacked rather than letting you fill whatever space remains in a container. Third, cabinets usually arrive during a narrow window of the fit-out: too early and they sit in an unprotected space; too late and flooring, worktops and appliance installation all stall behind them.

For that reason we treat the delivery plan as part of the product specification, not as something arranged after production. On a custom built-in kitchen cabinet order for an apartment or hotel floor, the drawing sign-off, the packaging schedule and the delivery address are confirmed before a single panel is cut.

What to Confirm Before Production Starts

Almost every delivery problem we see on a cabinet order traces back to something that was still open when production began. Work through this list with your supplier and get each item in writing:

  • Final dimensions and elevation drawings. Signed off by the person who will actually be on site, including floor levels, skirting, cornices and any service runs that affect carcass depth.
  • Appliance schedule. Built-in ovens, refrigerators, dishwashers and hobs with their published cut-out sizes. These determine tall unit and housing dimensions, and they are the item most often revised late.
  • Finish and material confirmation. Panel material, surface finish, colour reference and hardware — hinges, drawer runners, handles or touch-to-open mechanisms — matched to a physical sample rather than a screen image.
  • Room-by-room quantity breakdown. Each kitchen or unit listed separately, so crates can be labelled and unloaded to the right location instead of being sorted on arrival.
  • Delivery address and access route. Floor level, lift dimensions, stair width, gate height, whether a headland or hoist is available, and how close a truck can park.
  • Incoterms and the named place of delivery. Whether you are taking delivery at the port, at a forwarder's warehouse, or at the project address itself.

Packaging That Survives the Sea Leg

Cabinet packaging is designed around the journey. A container on a sea leg sits in high humidity and goes through repeated temperature swings, and crates are handled by forklift at both ends of the trip. Our usual approach for project cabinetry:

  • Knock-down where it helps, assembled where it is safer. Carcasses that can be flat-packed travel more efficiently; finished door panels and integrated units travel assembled to protect edges and alignment.
  • Edge and corner protection on every panel. Corner guards and edge banding protection on the visible faces, since damage on a door front cannot be touched up to match.
  • Separate packing for hardware. Hinges, runners, legs and brackets are boxed and documented against the crates they belong to, so nothing is discarded with the packaging.
  • Markings that site crews can read. Crate labels carry the unit code, room designation, crate number of a set and gross weight, so the right crate goes to the right kitchen without opening anything.
  • Loading sequence planned against unloading. Crates for the first rooms to be fitted are loaded so they come off first at your port.

Ask before you commit: request the packing list with crate dimensions and weights before booking inland transport at destination. Site access restrictions are far cheaper to solve on paper than with a crane call-out.

Choosing the Freight Route

Cabinets are dense, high-value cargo, so most project orders travel by sea in a shared or full container. Sea freight gives the best cost per cubic metre and is the natural choice once production is complete and the fit-out programme has slack. Air freight only makes sense for small replacement items — a handful of door panels or a set of tall units — where the extra freight cost is still cheaper than holding a site idle. Rail services sit between the two on some corridors and are worth pricing when the destination is inland.

Under our furniture logistics and door-to-door delivery service, freight forwarding by sea, air and rail is arranged together with customs paperwork, container loading plans, shipment tracking and delivery to the named address. That single coordination point matters on a cabinet order, because the container frequently carries other project lines alongside it — worktops, sinks and taps, lighting, flooring or handleless minimalist kitchen cabinets for a second unit type.

Customs Documents to Have Ready

Clearance delays cost more than the freight on most shipments, and a cabinet container is no exception. Prepare the paperwork with the same care as the packing list:

DocumentWhat it must get right
Commercial invoiceAccurate description of goods, value, currency and Incoterms; consistent with the purchase order.
Packing listCrate count, dimensions, weights and unit codes that match the labels on the crates themselves.
Bill of lading or air waybillConsignee and notify party spelled as your customs broker requires; correct port of discharge.
Certificate of originIssued for the shipment, not reused from an earlier consignment.
Import permits or declarationsHandled by your broker at destination; confirm requirements before dispatch, not after arrival.
Cargo insuranceInsured value and covered leg stated clearly, so a claim is not argued over afterwards.

Duty rates, import conditions and required declarations vary by destination country and change over time. Confirm the current requirements for your own country with your customs broker before the order is placed; we supply the shipping documents and coordinate on our side, but we cannot advise on your local import rules.

Planning the Arrival Around the Site Programme

The most common scheduling mistake is treating delivery as a single date. On a cabinet order there are four dates that have to line up:

  1. Site-ready date. When flooring, wall finishes and first-fix services in the kitchen area are complete enough to receive carcasses.
  2. Container discharge date. Set back from the site-ready date so there is buffer for clearance.
  3. Inland delivery date. Booked against confirmed access at the property, including lift or hoist availability.
  4. Installation start. Aligned with when worktops can be templated and appliances delivered.

On multi-unit projects, phase the shipment by unit type or building block rather than sending everything at once. Storage at a fit-out site is usually the scarcest resource, and crates stacked in a corridor get damaged. If your programme has an early handover for part of the building, say so when confirming the order — production and packing can be sequenced around it.

Checking the Delivery on Arrival

Whatever unloads the vehicle, inspect before you sign it off. Opening crates is not an admission of fault; it is how a claim stays valid.

  • Check crate count against the packing list before the vehicle leaves.
  • Photograph any damaged or crushed crates externally, then again once opened, with the label visible in frame.
  • Inspect door fronts and edges first, as these are the parts that cannot be repaired invisibly.
  • Cross-check hardware boxes against the documentation while the packaging is still intact.
  • Report any damage or shortage in writing within the claim period stated on the documents, with photos and crate numbers.

Our installation and after-sales support covers on-site installation, inspection and snag resolution, spare parts and replacement, and ongoing maintenance. Response-time commitments and warranty terms differ by project, so ask for the specific terms that apply to your order in writing rather than relying on what a product page states.

One Point of Control for the Whole Order

Cabinets rarely travel alone. A kitchen project touches flooring, wall panels, ceiling finishes, lighting and sanitaryware as well, and every additional supplier adds another set of dates to reconcile. Coordinating those lines under one turnkey interior project solution removes the handover gaps where cabinet orders usually go wrong: the worktop that arrives before the carcasses, the appliance that does not match the tall unit, the lighting circuit that was routed to the wrong island.

Where your design intent is a clean, handle-free run of cabinetry, our custom and OEM service covers bespoke dimensions, panel materials, finishes and hardware specification, with prototyping before the project run is produced. The same drawings then drive production, packing and delivery, which is exactly what keeps an international order predictable.

Send us your cabinet drawings and site address

Share the elevation drawings, appliance schedule, quantity breakdown by unit and the delivery address with access details. We will return a production plan, a packing and loading proposal with crate dimensions, and a freight option for your destination — so the delivery date is fixed before manufacturing starts.