Why Built-in Wardrobes Need a Written Plan Before Production Starts
A wardrobe that arrives on site and does not fit the wall is one of the most expensive avoidable problems in a residential fit-out. Because our Solid Color Melamine Wardrobes are made to measure, with finish, layout and dimensions specified for each project, the practical decisions have to be settled on paper before manufacturing begins. An installation plan is where those decisions get recorded: who measures what, which specification is being built, how the units reach the property, and who checks the work at handover. Below is the checklist we use internally when a melamine wardrobe package moves from quotation to production.
1. Measured Survey of Every Room in the Package
Take dimensions after the floor and wall finishes are decided, not before. Record for each room:
- Wall lengths at three heights and three widths, plus the out-of-plumb reading — melamine carcasses are manufactured to a fixed size and cannot be trimmed on site the way solid timber can.
- Floor-to-ceiling height, including any skirting, cornice, or raised platform that the unit has to clear.
- Positions of power outlets, switch plates, downlights, air-conditioning grilles, sprinkler heads and radiators, with distances from two reference walls.
- Door and window openings, opening direction, handle clearance, and the swing arc of any existing door that crosses the wardrobe run.
- Ceiling void depth and access hatches, if the top of the unit closes off a services zone.
Note which party supplies the survey. Where the client or their builder provides it, we work from those numbers and confirm them again against our own production drawings before cutting; where the site is still rough-in stage, we ask for the finished floor level in writing.
2. Confirmed Layout and Internal Configuration
The plan should carry one approved elevation per room, showing hanging zones, shelf heights, drawer stacks, and any drawer-focused or open display section. Fix these items on the drawing:
- Door type — hinged, sliding or open — and the clearance each type needs to operate.
- Rail heights and double-hang zones matched to the users, not to a default catalogue dimension.
- Drawer and tray positions relative to skirting and handles, so fronts do not foul adjacent units.
- Integrated lighting or mirror panels, with their power feed and switching shown on the electrical drawing.
Any change after sign-off is treated as a variation, because panel sizes, edge banding and hardware sets are ordered against the approved elevation.
3. Finish, Substrate and Edge Specification
Melamine wardrobes look simple from the outside, which is exactly why the specification needs to be explicit. The plan should state the board type, the decor reference, the edge treatment and the hardware brand and model, room by room. Our Melamine Wardrobes collection covers several surface directions — Matte Finish, Glossy Finish, Textured and Wood Grain — and each behaves differently under site lighting and daily handling. Record the following:
| Item to record | Why it belongs in the plan |
|---|---|
| Decor reference and sample approval date | Solid colour decors shift between batches; an approved physical sample settles colour match across rooms. |
| Surface sheen (matte, glossy, textured) | Gloss surfaces show fingerprints and edge light lines; matte shows scuffs more readily in high-traffic family rooms. |
| Edge banding material and colour | Visible edges define how the run reads as one piece or as separate boxes. |
| Hinges, slides, handles and soft-close spec | Hardware is replaced individually later; a model number in the plan saves a site visit. |
| Interior carcass colour | Interiors are often specified differently from fronts to control cost without changing the look of the room. |
4. Site Conditions and Interface Responsibilities
Most on-site failures come from an interface nobody owned. The plan should name the party responsible for each of these, with a date:
- Finished floor level and floor flatness across the wardrobe footprint.
- Wall plumb and packing, including any scribe or filler strip agreed in advance.
- Electrical first fix and second fix around integrated lighting and mirror panels.
- Protection of installed units while other trades finish the room.
- Storage location on site between delivery and installation, dry and off the ground.
5. Packaging, Access Route and Delivery Sequence
Built-in wardrobes arrive as panel packs, not as assembled furniture, so the plan has to trace the route from kerb to room. Confirm lift or stair dimensions, corridor turns, door widths, and whether panels need to be carried over a finished floor with protection boards. For apartments and villas on a single access point, we sequence the pack list by room so the first flat delivered is the first flat installed, rather than everything landing in one pile. Panel sizes are also checked against the tightest turn on that route during design, which prevents an oversized side panel that cannot reach its wall.
6. Installation Sequence and Fixing Method
Set out the order of work in the plan: pack check against the packing list, dry layout of carcasses, fixing method per wall build-up (masonry, stud, or tiled), levelling across the run, door alignment, then hardware adjustment. Note that wall fixings must match the substrate — a fixing suitable for solid masonry will not hold a freestanding-height unit on plasterboard alone, and the plan should say what blocking or backing the builder provides and where.
7. Snag List, Handover and After-sales
Close the plan with an inspection pass: door gaps and alignment, drawer run-out, soft-close function, panel condition after handling, and colour match between rooms. Items are recorded as snags with owners and dates. Spares worth listing in the handover file are hinges, slides, handles and one spare shelf pin set per room type; keeping the model numbers on file makes a later replacement an order rather than a site survey. Our installation and after-sales support covers on-site fitting, inspection, warranty coverage, spare parts and ongoing maintenance — see Installation & After-sales Support.
How the Plan Travels Through a Project
For villa and apartment packages, wardrobe decisions rarely stand alone: kitchen cabinetry, vanities, doors and wall panelling share the same site programme and the same trades. Coordinating them through one procurement workflow — design and planning, production, logistics, installation, after-sales — avoids the situation where wardrobes are scheduled for a week the electricians have already left. We work that way across turnkey interior project solutions, and the same plan format applies whether the package is one bedroom or a whole villa.
Before you send an enquiry: have your measured survey, finished floor levels, room elevations and preferred melamine decor reference ready. With those four inputs we can return production drawings for the full wardrobe package and a delivery sequence matched to your site programme.
Frequently Asked Questions
When should the final survey be taken? After the finished floor and wall finishes are set. Measuring at rough-in stage leaves tolerances that a fixed-size melamine carcass cannot absorb.
Can dimensions be adjusted after production starts? Panel sizes, edge banding and hardware sets are ordered against the approved elevation, so changes become a variation with re-made panels. Confirm the drawing before release.
Which rooms should use which melamine finish? Choose by traffic and light. Glossy surfaces read bright but show handling marks; matte and textured surfaces hide daily wear better in family bedrooms and shared corridors. Specify per room in the plan rather than one finish for the whole project.
Who installs the units? Either our team or your local crew, provided the fixing method, wall build-up and blocking are stated in the plan before the panels ship.
SANTERSON is a China-based furniture and building materials manufacturer supplying made-to-measure built-in furniture for residential and hospitality projects. For wardrobe packages with confirmed dimensions, finish references and site access details, our team returns drawings, a specification sheet and a delivery sequence in one package.