A procurement brief that names a wall finish but leaves the acoustic requirement to chance is where most panel packages go wrong. Site teams receive panels that look right on the drawing and behave badly in the room. The checklist below sets out what a buyer should actually put in writing when specifying Santerson Acoustic Panels, so quotations from the factory and expectations on site match each other.

Start with the rooms, not the finish

Before any finish sample is requested, list every space where an acoustic wall treatment is expected: bedrooms, media and family rooms, home offices, guest suites, meeting rooms, restaurant or lounge areas. For each space record what the occupants complain about: sound travelling between rooms, echo and reverberation inside a room, or noise from a corridor or plant room. These are different problems, and they point to different build-ups.

State this in the brief as a plain description of the problem per room, together with the room's dimensions and the wall area involved. A supplier working from "living room needs acoustic panels" will quote a decorative panel; a supplier working from "hard plastered lounge, reverberant during evening use, approximately 40 square metres of wall available for treatment" can propose something that addresses the complaint.

Fix the scope: fixed cladding or operable screening

The catalogue separates two product families, and choosing between them early avoids re-work at the quotation stage:

  • Santerson Acoustic Panels sit within the Paneling Systems collection: fixed wall cladding for wall system projects, where finish, layout and dimensions are set per space.
  • Santerson Acoustic Sliding Panels sit within the Sliding Panel Systems collection: acoustic panels on an operable track, used where a wall or partition also has to open and close.

The decision is functional before it is aesthetic. A room that must be subdivided for part of the day needs sliding panels, which brings tracks, hardware and clear opening dimensions into the scope. A room where the wall stays put only needs fixed cladding, but the substrate, the fixing method and the panel layout become the items to confirm.

What must appear in the brief for each panel type

Both collections are sold as configurable products with made-to-measure sizing and a choice of material and finish, so the brief has to carry the detail that a stock item would normally come with.

Brief itemWhat to write down
Location and quantityRoom name, wall elevation or drawing reference, panel area in square metres per elevation. Flag any opening that interrupts the run.
Panel typeFixed cladding or sliding system. For sliding: number of leaves, stacking direction, and whether the track is exposed or recessed.
DimensionsFloor-to-ceiling heights at high and low points, reveal depths, and any setting-out for skirting, architraves or service runs behind the panel line.
FinishRequired colour, texture and sheen, plus whether the finish must match an existing joinery item such as cabinetry or doors. Related finishes in the same collections, such as textured, glass and glossy, or stone and marble panels, are useful reference points when matching.
Substrate and fixingWhat the panels fix to, whether a battened frame is required, and how services, sockets and switches are to be cut out or relocated.
Acoustic intentThe performance the project requires for that space, stated as a requirement. Ask the factory to confirm which configuration meets it for the selected build-up rather than assuming the decorative panel already does.
Interface tradesWho supplies lighting cut-outs and downlights behind the panels, skirting transitions, flooring thresholds, and the adjoining plaster or joinery lines.
Delivery and installationShip-to address, delivery mode, who installs, and the sequence relative to wet trades and flooring. Panel packages installed before painting and flooring are finished create snag lists nobody wants.
Because these listings are configurable rather than stocked items, acoustic performance should be confirmed for the exact configuration quoted, including panel build-up, thickness and fixings, and recorded in the order documents. Do not carry a performance figure from one product family across to another.

Close the gaps that cause change orders

Three omissions produce most of the cost variation on panel packages:

  • Unconfirmed dimensions on site. Made-to-measure panels are only as good as the measured openings. Have heights and setting-out lines checked on site after plastering, before release for production.
  • Hardware treated as an afterthought. For sliding systems, track type, leaf count, running gear and opening dimensions must be in the quotation. A change here alters both price and the structural support above the opening.
  • Finish matching left verbal. Request a physical sample or a signed-off finish reference where panels abut factory-made joinery. Screens and partitions elsewhere in the same project should be specified against the same reference so metal, timber and panel finishes stay coherent.

If the wider fit-out is also being sourced from the same supplier, such as cabinetry, doors, wall cladding and built-in joinery, state that on the enquiry. One coordinated set of drawings and one finish schedule across the package removes the mismatch between trades that a piecemeal order invites.

Where the panels come from

SANTERSON presents itself as a China-based furniture and building materials manufacturer and one-stop supplier, with named services covering custom and OEM production, door-to-door logistics, installation support and after-sales. In procurement terms that means one party can be made accountable for the made-to-measure run, the finish schedule and the delivery, provided your brief states those responsibilities instead of assuming them.

Useful questions to include in the enquiry: what the factory needs from the site team before release for production; how finish samples are issued and signed off; what the hardware schedule for a sliding system covers; and how the panel delivery is sequenced against other fit-out trades. Panel packages that land before plastering and flooring are finished turn into snag lists nobody owns.

Sample brief wording

A short paragraph in the enquiry does most of the work:

"Project: [name], [city]. Scope: acoustic wall treatment to bedrooms, media room and two meeting rooms; approximately [x] square metres of fixed cladding plus one operable partition of [n] leaves between lounge and dining. Drawings attached with elevations and measured openings. Required finish to match joinery reference [ref]. Please confirm panel build-up, overall thickness, fixing detail, acoustic performance for the quoted configuration, hardware schedule for the sliding system, lead time to [port or site], and what you require from the site team before release for production."

Send that with drawings and a measured dimension sheet, and the quotation comes back comparable line by line, which is what lets you compare two bids instead of two guesses.