Wood panel partitions look simple on a drawing: a run of panelling that divides a bathroom, dresses a wall and hides a door. They cause trouble on site when the quantities are guessed and each item is ordered on its own. This guide sets out how to count what you need, keep the matching items together and place one coordinated order instead of chasing parts after the walls start going up.
What a Wood Panel Partition Actually Includes
Before counting anything, be clear about where wood panelling sits in your package. In villa and apartment work we normally supply it as part of our wood panel partitions, made to measure within the Custom Partitions & Paneling collection, alongside wall panel systems, custom niche paneling and integrated door & paneling. Each is built to the dimensions of the room it belongs to, with the finish and layout specified per project.
One point that saves arguments later: panelling is not a stock item you count in boxes. It is cut from your dimensions, so the quantity question is really "how many wall runs, how many panels per run, and what else has to arrive with them".
Step 1: Break the Job into Wall Runs
Take each room one at a time and list every surface that will be panelled. A single bathroom commonly contains four or five separate runs, and each behaves differently:
- The wet run. Panelling behind the basin, along the shower wall or wrapping a bath surround. This is where niche positions and waterproofing details have to be settled before anything is cut.
- The storage run. Panelling that carries built-in cabinets, mirrors or open shelving. Panel widths need to align with the units in front of them.
- The concealed-door run. Where a door disappears into the panelling, the panel layout is dictated by the door size and its swing, not by aesthetics alone.
- The return and reveal runs. Reveals around openings, returns at external corners, bulkheads above doors. These are small pieces, and they are the ones that go missing.
Give every run a mark on the drawing (Bathroom 01 / Run A, and so on) and let that mark follow the item through your schedule, your purchase order and the delivery label. It is the cheapest way to keep a site team from guessing.
Step 2: Set Out the Panels Before You Count Them
Counting panels straight off an elevation view produces numbers nobody can build. Set out each run first, then count:
- Pick one panel width and hold it. A consistent module across a room makes the joints read cleanly and keeps spare stock meaningful. Common practice is to choose the module from the widest uninterrupted run, so you cut off your narrow panels at the concealed corners rather than in the middle of the wall.
- Position the vertical joints around features, not through them. Niche edges, mirror edges, cabinet edges and door frames should land on a joint or sit centred inside a panel. Decide this before quantities are fixed.
- Check heights against ceiling level variations. Slab levels, screed depths and ceiling grids change finished heights from room to room. Panels cut for one bathroom rarely drop straight into another, even on identical floors.
- Read the corners. External corners are usually returned as solid pieces rather than mitred sheet edges; internal corners need a setting-out decision too. Note which corners you mean before you order.
Step 3: Build a Quantity Schedule That Matches How You Order
A useful schedule row answers four questions at once: what it is, where it goes, how many, and what it must arrive with. Something like this, one row per run:
| Item mark | Description | Where it goes | Quantity basis | Must be ordered together with |
|---|---|---|---|---|
| B01-A | Panel run, basin wall | Bathroom 01, Level 3 | Panels per set-out; add the fixed pieces separately | Niche frame, mirror fixing pack, vanity unit |
| B01-B | Concealed door and surrounding panels | Bathroom 01, entry wall | 1 door plus panel layout either side | Concealed door hardware, matching finish sample |
| B02-A | Shower surround with niches | Bathroom 02 | Panels per set-out; niches counted individually | Niche units, shower valve positions |
| LD-01 | Living wall panelling and returns | Living / dining, Level 2 | Panels plus corner and reveal pieces | Cabinet run, integrated lighting provisions |
Two habits make the schedule worth more than a take-off sheet. First, keep panels, niche units, doors and reveals as separate lines even when they share one finish, because they are manufactured differently and travel in different bundles. Second, record the quantity basis rather than only a number, so that whoever reviews the order knows whether you counted panels, runs or pieces.
Step 4: Coordinate the Products That Touch the Panelling
This is where most project delays come from. Timber panelling becomes the visible background for half of the bathroom package, so anything fixed to it has to be decided at the same time.
Cabinetry and built-in storage
Vanity units, tall cabinets and open shelving sit against or in front of the panelled wall. Their depths set the reveal at the panel edge, and their fixing method has to be designed into the panel build-up rather than improvised on site. Where a cabinet is part of the same fit-out package, order it with the panelling so the carcass dimensions and panel thickness are reconciled in one shop drawing.
Niches, mirrors and glass
Niche recesses built into the custom niche paneling are fixed in position the moment those panels are manufactured. Mirrors, glass partitions and illuminated cabinets therefore need their positions, sizes and fixing details confirmed before any panel is cut. Cutting an opening into a finished panel is not a site adjustment.
Doors
A concealed or flush door only works if the leaf, frame and surrounding panels are made to the same module and finish. Where doors sit inside a panelled wall, treat them as one assembly in your schedule; see integrated door & paneling for the matching product line.
Lighting, taps and outlets
Downlights, wall sconces, vanity lights, shower mixers and sockets all penetrate the panel line. Each penetration needs a position on the set-out drawing, and first-fix wiring and pipework must be in place before panels go on. Record these as part of the run, not in a separate electrical schedule that nobody cross-checks.
Adjoining finishes
Flooring, stone and tile abut the panel edges. Where engineered timber flooring or stone cladding meets the panelling, decide which material takes the movement joint and what trim detail closes the gap. Put that detail on the drawing before quantities are locked.
Step 5: Group the Order by Room, Not by Trade
Once the schedule is complete, re-sort it by room. A purchase order that reads "everything for Bathroom 01" matches how a site team actually works, and it exposes missing items while there is still time to add them. It also lets us pack and ship by room mark, so a container arrives labelled in the same language the installers are reading.
For multi-unit jobs, take one full room as a prototype: order it first, install it, check levels and joints, then release the repeating quantities. Identical floors are not identical buildings, and one installed room tells you more than any drawing review.
Step 6: Sequence Production and Delivery Against Site Programme
Panelling is a late trade with an early decision deadline. Work backwards from your install date:
- Design freeze. Set-out drawings, finishes, niche positions, door positions and penetrations all confirmed.
- Site verification. As-built dimensions and finished levels checked against the drawings; changes recorded before manufacturing starts.
- Production. Panels, doors, niches and matching joinery made together so finishes come from one batch.
- Packaging and shipping. Bundles marked by room and run, with the small pieces (reveals, corners, fixings) packed with the run they belong to rather than loose in a shared box.
- Delivery and install. First-fix complete, room closed and dry, panels installed from the largest run inward.
Our logistics and door-to-door delivery service covers freight arrangements, packing lists and container loading, and our installation and after-sales support team handles site fitting and inspection. Import terms, transit time and on-site attendance are agreed per project, so confirm them for your specific delivery location rather than assuming a standard service level.
Pre-Order Checklist
Confirm before releasing the order
- Set-out drawing approved for every run, with panel module agreed
- Niche, mirror, cabinet and door positions marked on the set-out
- All penetrations (lighting, taps, sockets, shower valves) located on the drawing
- Finished floor and ceiling levels confirmed for each room
- As-built wall dimensions checked against the drawings
- Finish reference agreed from a physical sample, including any grain direction
- Corner, reveal and trim pieces listed as separate line items
- Spare panels ordered for at least one repeat unit on multi-unit jobs
- Fixing method designed into the panel build-up, not left to site
- Packing marked by room and run mark
How a One-Stop Package Reduces Coordination Work
The reason we push clients toward a single package is not convenience for its own sake. When panelling, cabinets, doors, vanities and matching joinery come from one manufacturer, the panel thickness, cabinet depths and door reveals are reconciled in one set of shop drawings, finishes come from the same production batch, and any dimension that changes gets changed once. As a furniture and building materials manufacturer working on villa and hospitality projects since 2008, we handle this as part of our one-stop solution service: design consultation and space planning, material selection and product specification, manufacturing and quality control, project management, then installation and handover.
Where a project needs a bespoke layout, our custom & OEM service covers made-to-measure sizing, material and finish selection, and prototype review before the full quantity is released.
Send Us Your Schedule
Get a coordinated quotation
Send the room schedule, set-out drawings and target install dates for your project. We will check the panel quantities against the adjoining products (cabinets, doors, niches, vanities and lighting), flag anything missing, and return an itemised quotation grouped by room so the order matches how your site is built. Contact us through the contact page to start that review.