A materials schedule that lists wardrobes as one line item is where most finish-related rework begins. On villa and apartment packages, joinery is produced once, delivered with everything else, and installed inside a narrow window, so the wardrobe specification has to be settled at the same time as the flooring, wall panelling and lighting it sits against. This guide explains how we carry Neutral Tone Lacquer Wardrobes through a whole-project materials schedule at SANTERSON — from the finish sample board to the room-by-room sizing sheet — so that procurement, production and site installation read the same document.

Why Wardrobes Belong in the Materials Schedule, Not the Furniture List

Loose furniture can be swapped between order and handover. Built-in wardrobes cannot. Their dimensions are fixed by the structure, their finish has to match doors, panelling and vanities produced elsewhere in the same package, and their panels travel in the same containers as flooring and kitchen cabinetry — which is why we schedule them alongside Charcoal European Oak Engineered Wood Flooring. When a wardrobe line appears only on a furniture list, three familiar problems follow: the lacquer tone is approved from a photograph rather than a physical sample; the floor build-up is decided after the wardrobe carcass depth is set; and the lighting inside the niche is ordered by the electrical package with no reference to the joinery drawing.

We treat each wardrobe run as a scheduled material, with a code, a finish reference, a location list and a release date. That single change is what keeps the joinery package aligned with the rest of the fit-out.

Step 1 — Fix the Finish Reference Before Any Dimension Is Signed Off

Neutral tone is a family, not a colour. Warm greys, putty, taupe, oat and soft beige lacquers all read as "neutral" on a mood board and look completely different side by side under site lighting. Our first scheduled action is a physical sample board for the lacquer finish, issued against the same board that carries the wall panels, doors and any Santerson Matte Lacquer Panels used in the same rooms.

  • Approve the sample under the light temperature actually planned for the bedroom, not daylight-balanced showroom light.
  • Compare the lacquer sample against the flooring sample and the carpet or rug sample in one layout, because neutral tones shift visibly next to oak grain and wool pile.
  • Record the approved finish as a code on the schedule with the sample date and the approver's name, so a later substitution has to be raised formally.
  • Keep one signed physical copy of each approved board in the project file; a colour seen in an email is not an approval record.

For projects that mix sheen levels — a matte wardrobe front against a higher-sheen vanity, for example — we schedule those as separate line items with their own sample approvals. Sheen changes how a neutral reads at the edge of a panel, and it is the most common cause of "the colour changed on site" complaints.

Step 2 — Build the Room-by-Room Sizing Sheet

The Lacquer Wardrobes collection is made to measure: sizing, material and finish options, and internal layout are set per project. That flexibility only helps if the dimensions arrive complete. Our scheduling sheet carries one row per wardrobe run, not one row per product, and each row records what production actually needs.

Schedule FieldWhat It Prevents on Site
Room and unit reference, matched to the drawing setContainers arriving with panels labelled for a room that no longer exists on the revised drawings.
Clear opening width and height, plus floor finish build-upA wardrobe ordered to a structural dimension that ignores the thickness of flooring or screed laid first.
Carcass depth and door swing or sliding configurationDoors fouling a bed, a vanity drawer or a corridor on completion.
Internal layout: hanging heights, drawers, shelves, lighting provisionsAn interior configured for short hanging in a master bedroom meant to hold long garments.
Approved finish code and sheenA neutral tone approved for one block being replicated across another with different lighting.
Release date and container groupJoinery shipped before the wet trades in that room are finished, or shipped twice.

Where a project also includes walk-in dressings, we schedule those runs separately from bedroom wardrobes. A Boutique Style Walk in Wardrobe carries different internal layouts, glass and lacquer combinations, and island or perimeter arrangements, so it cannot share a single quantity with bedroom units without losing that detail.

Step 3 — Coordinate the Wardrobe Line Against Adjacent Trades

A wardrobe line only becomes buildable once its neighbours on the schedule are cross-checked. In our project management we run three checks against the joinery rows:

Flooring and skirting

Confirm which goes first, flooring or wardrobe, and record it on the row. Where flooring runs under the carcass, the schedule must show the build-up thickness so the base panel height is correct at production, not adjusted with packing pieces on site. The skirting detail at the wardrobe line is agreed with the same reference used for doors.

Wall panels and ceiling

Where a headboard wall continues behind or beside the unit, the panel module size and its shadow gap are set together with the wardrobe reveal. For ceilings, an aluminium strip or baffle ceiling above a wardrobe run needs its access requirement recorded before the carcass is built to the soffit.

Electrical and lighting

Internal wardrobe lighting needs a driver location, a switch or sensor position, and a cable route that exists in the first-fix drawing. We mark these on the joinery elevation and issue it to the electrical package rather than leaving it as an installation-stage variation.

Step 4 — Sequence Production and Delivery Inside the Container Plan

Because furniture and building materials come from the same manufacturing group, wardrobe panels, Custom Built-in Kitchen Cabinets, doors and panelling can be released on one production plan and loaded as one coordinated shipment. The schedule then does double duty: it is the procurement document, and it is the packing list reference. Shipment paperwork sits inside our Furniture Logistics and Door-to-door Delivery service, which covers freight forwarding, customs documentation and container loading.

  • Release joinery for production only after the finish board is signed and the room dimensions are frozen; anything released early becomes a variation.
  • Group wardrobe panels by room in the packing list, using the same room references as the drawings.
  • Ship joinery after the wet trades in those rooms are complete, in line with the delivery plan agreed at quotation stage.
  • Keep a spare panel allowance for high-traffic units on the same line item, so replacements do not require a new colour match years later.

Step 5 — Install, Inspect and Hand Over Against the Same Row

At installation the schedule row becomes the inspection sheet. Our installers work room by room against the references already on the document: level and plumb of the carcass, door alignment and gap consistency, drawer runners under load, internal layout against the approved elevation, and finish condition after handling. Snags are logged against the same row, which is what makes the follow-up with the factory specific instead of a photograph and a guess.

The handover pack then carries the approved finish codes, the internal layouts as built, and the spare-panel allowance. For a client managing several villas or an apartment portfolio, that record is what allows a matching repair years later without re-approving a colour.

Dimensions, material choices and selected specifications are confirmed per project before production release. Finish names on drawings are matched to the signed sample board, not to a catalogue photograph.

A Practical Checklist for Your Next Schedule Revision

  • Does every wardrobe run have its own row with room reference, dimensions and finish code?
  • Is the lacquer sample physically approved against flooring, panelling and door samples?
  • Are sheen levels separated into distinct line items?
  • Is the floor build-up recorded before carcass heights are fixed?
  • Has the electrical package received the joinery elevation with lighting provisions?
  • Does the packing list use the same room references as the drawings?
  • Is there a spare-panel allowance on high-use units?

If you are assembling a materials schedule for a villa, apartment or hospitality package and want the joinery rows built from drawings you already have, send us the drawing set and finish direction. We will return a wardrobe schedule with room-by-room sizing, finish sample boards and a production and delivery sequence aligned to your other fit-out packages.