A wardrobe package is rarely the first line item a project team argues about, and it is usually the one that arrives last and has to be installed first. Aluminum frame glass wardrobes sit at the junction of joinery, glazing, hardware and interior finish, so a thin enquiry produces a thin quotation and, later, a change order. The brief below is the structure we ask buyers, contractors and design coordinators to work through before a price is requested, so that drawings, samples and production all start from the same set of decisions.
Start With the Room Data, Not the Door Style
Made-to-measure built-in wardrobes are dimension-driven products. Before anyone discusses glass colour or handle profile, the brief should record what the site can actually deliver. For each wardrobe wall, capture:
- Finished floor level and finished ceiling or soffit level, measured at both ends of the run, not one average figure.
- Wall construction and its ability to take fixings: masonry, stud partition with noggins, tiled surface or a previously lined wall.
- The position of skirting, architrave, cornices, downlights, air-conditioning grilles, curtain boxes and any projection into the wardrobe zone.
- Door swing and circulation clearances in front of the wardrobe, which decide whether hinged, sliding or open-front layouts are workable in that room.
- Levels and setting-out drawings for rooms where the wardrobe face is intended to align with wall panelling, doors or headboard niches.
Where a project has several unit types repeated across rooms, state clearly which dimensions are fixed by design and which may vary on site. That single line in the brief prevents every wardrobe from being re-surveyed at production stage.
Frame: Profile, Finish and Where It Is Exposed
The aluminium profile is what gives this product its shadow line, so specify it as a drawing item rather than an adjective. In the brief we ask for:
| Frame decision | What to write in the brief |
|---|---|
| Profile shape and sight line | Square, shaved or rounded edge; whether the frame is exposed on both faces or only on the room side. |
| Surface finish | Anodised, powder-coated or wood-effect, with a named colour reference and a physical sample approved before production. |
| Frame-to-panel junction | Whether glass sits in a rebate or a butt joint, and whether a shadow gap is required against the wall. |
| Integration items | Matching frames around corner returns and end panels, and the same profile used where different glass appearances are specified for different room types on one floor. |
Colour reference matters more than it looks on a specification sheet. Two suppliers can both read "matte bronze" and ship visibly different profiles against the same anodised window frame, so record the sample code and who approved it.
Glass: Type, Appearance and Handling
Glass is the visible surface and also the heaviest component, so both appearance and safety handling belong in the brief. Specify:
- Glass type and thickness as stated by the manufacturer for the door system chosen; do not transfer a thickness from another collection.
- Appearance: clear, frosted, ribbed or smoked. Order one physical sample per appearance you intend to use and review it under the actual room lighting; the catalogue lists clear glass aluminium frame wardrobes and frosted glass aluminium frame wardrobes as separate records, so a sample request can follow the same split.
- Edge treatment and whether any surface is printed, lacquered or laminated on the reverse.
- Handling assumptions: door weight, the number of people needed to place a leaf, and access route from lift to room, including corridor widths and turning radii.
Interior Layout and Accessories
The carcass is standard; the interior is where room programmes differ. Give the manufacturer a per-unit-type layout schedule covering hanging heights, shelf spans, drawer stacks, tray and trouser rails, shoe shelving, lighting provision and any mirror or glass walk in wardrobe layout used in larger rooms. State which items are supplied by the wardrobe manufacturer and which come from another trade, because a light strip wired by others but rebated by us has to be cut at the factory.
For hospitality and villa projects with mixed unit types, a simple table of unit type against room number is enough. It lets production group identical carcasses and lets the site team match crates to rooms on delivery day.
Hardware, Movement and Tolerances
Sliding systems go wrong on installation accuracy far more often than on component quality, and hinged doors show misalignment the same way. The brief should record:
- Track type, whether the top or bottom track carries the load, and the maximum door leaf size and weight the system is rated for.
- Hinge, damper and soft-close specification, with a brand or model reference where the design requires one.
- For mirror sliding door wardrobe variants, confirm which face is mirrored and whether the mirror sits in the same aluminium profile as the glass leaves.
- Floor tolerance the installation can accept, and who is responsible for levelling the floor or building the boxing before the wardrobes arrive.
- Adjustment access after handover, so maintenance teams know how to re-level a leaf without removing the frame.
Documentation and Approval Sequence
A procurement brief that only asks for a price produces a number with no agreed basis. We recommend releasing information in four stages, each with an owner and a date:
- Enquiry pack: room schedule, elevations at finished levels, frame and glass shortlist, unit-type layout schedule.
- Shop drawings: manufacturer-issued production drawings for each unit type, marked with dimensions taken from site survey rather than design intent only.
- Sample approval: one physical wardrobe or one door leaf plus profile and glass samples, signed off with a date and approver name.
- Release to production: written confirmation of approved drawings and samples, together with the delivery sequence by room or floor.
This sequence is the same one SANTERSON applies across its custom and OEM service, where material, finish and dimension are confirmed against approved drawings before manufacturing starts.
Delivery, Storage and Installation Responsibilities
Wardrobes arrive as a kit: panels, glass leaves, tracks, hardware in labelled cartons. A brief that ignores logistics creates damage at the loading bay. Include:
- Packing standard and crate labelling against room numbers, agreed before shipment.
- Delivery window, dock size and storage area conditions: dry, level, off the traffic route, and accessible after other trades have finished wet work.
- Who supplies installers, who provides silicone and making-good materials, and who protects adjacent finishes during installation.
- The snag list method and what constitutes completion for handover.
For international projects these points extend to freight and documentation. SANTERSON arranges sea, air and rail forwarding with customs paperwork and door-to-door delivery under its logistics service, then supports on-site installation and after-sales work through installation and after-sales support. Import terms, duties and transit arrangements are confirmed project by project rather than assumed.
Common Specification Gaps We See
- Finished levels omitted, so carcass heights are quoted from design drawings that have not yet absorbed floor build-up.
- Frame colour specified in words only, with no approved physical sample on file.
- Glass thickness carried over from a different door system instead of the one being ordered.
- Interior accessories listed without spans and load assumptions, which changes shelf material and support.
- No named responsibility for floor levelling, boxing or electrical connection to internal lighting.
- Delivery sequence missing, so all crates land in one drop with no room allocation.
A Short Checklist for the Brief
- Room schedule with unit types, quantities and finished-level dimensions
- Wall build-up and fixing method confirmed by the main contractor
- Frame profile drawing plus approved colour sample reference
- Glass type, thickness and appearance per room type, with samples held on site
- Interior layout schedule per unit type, including lighting provision
- Hardware model references and maximum leaf weight and size
- Sample unit released for approval before bulk production
- Crate labelling, delivery sequence and storage conditions agreed
- Named owners for floor preparation, boxing and electrical connection
- Snag process and handover criteria written into the order
If you are assembling a wardrobe package alongside other joinery, wall panelling and doors for a villa or hospitality project, send us the room schedule and elevations and we will return production drawings, a material schedule and an itemised quotation for aluminium frame glass wardrobes and matching built-in furniture.