Why Flush Sliding Doors Need Their Own Delivery Slot
A Santerson flush sliding door is not an item you can drop on site and hang the same afternoon. The panels are made to measure for each opening, and the way they sit — flush with the finished wall face — depends entirely on what happens before them: the floor level, the wall build-up, the track position and the clearance for the sliding pocket or surface rail. When doors arrive early, they spend weeks in a corridor absorbing moisture and getting knocked. When they arrive late, the painting crew has already closed the wall and the joinery team has moved to another job.
On villa and apartment projects we supply across Australia and elsewhere, the door package is usually the last interior element to be fixed and the first one blamed when a handover date slips. The fix is not more expediting emails. It is deciding, on paper and early, which site conditions must be complete before each door panel can leave the factory, and which must be complete before it can be fixed.
Step 1: Lock the Openings Before Production Starts
Every flush sliding door in the range is configured per project — dimensions, layout, material and finish are specified to suit the space. That flexibility only pays off if the numbers behind it are final. Before we release panels to production, we need the following confirmed by the site team:
- Finished floor level at every doorway, including any screed, adhesive or tile build-up that has not yet been laid.
- Finished wall face, meaning the plasterboard face plus the intended lining thickness, so the panel and track sit flush once decorating is complete.
- Opening width and height at three points each, with the tolerance you want us to allow for on-site adjustment.
- Sliding configuration: pocket (wall-recessed) or surface-mounted rail, panel count, and which direction each panel travels.
- Finish selection, matched against a physical sample rather than a screen image, because veneer, lacquer and panel colour read differently under site lighting.
Step 2: Split the Order into Track Delivery and Panel Delivery
The single most useful planning decision is to separate the hardware from the leaves. Tracks, pockets and frames can go to site months early, while walls are still open. Decorative panels should arrive as close to handover as the packaging allows.
| Element | When it should reach site | Why that timing |
|---|---|---|
| Tracks, rails, pocket frames, wall fixings | Before wall lining closes | They are built into the wall; once plasterboard is up, retrofitting means opening the wall again. |
| Door panels and handles | After painting and flooring are complete | Panels are the visible finish. Early arrival risks impact damage, paint splashes and moisture warping. |
| Wardrobes and matching flush interior doors from the same joinery package | With the panels, in the same container | One fix-out visit covers the whole timber package instead of two mobilisations. |
Step 3: Set the Site Readiness Checklist Before Booking Freight
We arrange sea, air or rail freight with customs paperwork and door-to-door delivery under our logistics and door-to-door delivery service. The container will arrive on the date agreed. What we cannot control is whether the opening is ready when it lands. Before you confirm a shipping window, walk the site against this list:
- Wet trades in the relevant rooms — screed, tiling, plastering, first-coat paint — signed off and dry.
- Roof or temporary weather protection in place, so panels can be stored indoors rather than under a tarp.
- A flat, dry storage area with enough length for full-height panels stored upright, not leaning.
- Access route confirmed: lift dimensions, stair widths and turning radii measured against the packed panel sizes we send you in the packing list.
- The fix-out team booked for a defined window, ideally five to seven working days for a typical villa door package, so panels do not sit on site waiting for labour.
Step 4: Sequence Installation Against the Other Trades
Flush detailing is unforgiving of poor sequence. If skirting, architrave or stone sills are installed before the track line is set out, the reveal will not run true. Our recommended order for each opening:
- Set out the track line and panel drop against the finished floor and wall datums, marked on site.
- Fix tracks and frames, then re-check level and alignment before anything covers them.
- Complete wall finishes — lining, jointing, paint — up to the panel edge.
- Hang panels, adjust runners for smooth travel, and set the gap between panel and wall face.
- Fit handles and hardware, then run each door open and closed several times under supervision.
- Snag walk with your site supervisor: alignment, operation, finish defects, and any adjustment needed after building movement.
Our installation and after-sales support covers on-site installation guidance, inspection and snagging, spare parts and ongoing maintenance. On larger door packages we prefer our installer to work alongside your joinery crew for the first openings; once the setting-out method is agreed, your team repeats it across the remaining doors.
Step 5: Document What Is Agreed, in Writing, Twice
Two confirmations prevent most disputes. The first is the specification sign-off before production: dimensions, finish sample reference, hardware selection and configuration. The second is a site readiness confirmation before dispatch — one email from your site manager stating that the checklist above is complete for the rooms in that shipment. Neither takes long. Both protect the handover date.
If you are coordinating doors alongside other fit-out elements — flush wall aligned doors, panelling, wardrobes or cabinetry in the same villa package — group them under one procurement schedule with a single set of datums. Doors and wall panels ordered against different measurements is the most common cause of rework we see on residential projects.
Planning a door package for a villa or apartment project?
Send us your opening schedule and finish preferences. We will confirm what can be made to measure, flag any openings that need site verification, and propose a track-and-panel delivery split that fits your programme.
Contact PHILLIP — Phone / WhatsApp: +86-13928214007 · Email: santerson@qq.com