Media storage is the item most often left out of a materials schedule until fit-out is already underway. It arrives as a late variation because nobody decided who owns the wall behind the television, where the decoder and router sit, how the cables reach them, or what happens when the operator needs to swap a device some years after handover. A built-in media unit settles all four questions at once — but only if it is scheduled with the joinery, the AV package and the electrical first-fix in the same column of the same spreadsheet. Below is how we place integrated media storage into a whole-project schedule for villas, serviced apartments and hospitality rooms, using our floating TV units as the reference product family.

Why media storage belongs in the materials schedule, not the AV variation

A loose media cabinet can be bought late. A built-in one cannot, because it fixes dimensions that other trades depend on: the wall build-up and its load capacity, the position of back boxes and trunking, the stone or panel interface, and in a guest room the maintenance access to equipment. If the unit is only priced as furniture, those dependencies fall between three separate packages and someone pays for them twice.

Scheduling it as an interior fixture means the unit appears with a line item, a drawing reference, a lead time and an installation sequence — the same treatment as cabinetry and wardrobes. That single change removes most of the rework we see on site: TV walls rebuilt to carry weight, patch-and-repaint around wrongly placed cable ports, and equipment cupboards that cannot be opened because a drawer was built in front of them.

What to specify for an integrated media unit

The Santerson floating TV units in our TV cabinets and media units collection are wall-mounted, made-to-measure pieces with material, finish and layout options set per project. That is the configuration repeat-unit projects now favour: the floor stays clear, housekeeping has no furniture leg to work around, and the wall build-up is engineered once and repeated. Write these parameters into the schedule rather than describing the item as "media cabinet as per design":

Schedule fieldWhat to record
Mounting and substrateWall type, lining material and the fixing method for that lining; for stud or clad walls, state the reinforcement band, its height and who installs it. This is a structural note, not a joinery note.
Screen envelopeScreen size range, mounting type (fixed, tilt, pull-out arm), the recess or reveal dimension, and the ventilation gap required around any equipment enclosed behind a door.
Cable routingNumber and diameter of routes, their entry and exit points, trunking or grommet details, and whether power sits inside the cabinet or in an adjacent accessible position.
Equipment compartmentWhich devices live inside — decoder, router, soundbar, casting box — with internal shelf pitch, adjustable fixing for device brackets, and door type (hinged, flap, bi-fold) checked against the door's swing clearance.
FinishesPanel material, surface finish, edge treatment and the matching tone against adjacent joinery; note whether internal cabinet faces are finished or raw.
HardwareHinges, runners, soft-close fittings and wall-mount brackets by brand and model, with a spares allowance per room type for post-handover maintenance.
Interface ownersNamed responsibility for the reinforcement band, first-fix electrical, TV mounting hardware, AV commissioning and final snagging.

Product pages describe materials and durability in marketing terms. Confirm board grade, load rating, edge banding and hardware cycle data from samples and test documentation before release for production — do not carry catalogue wording into a technical submittal.

Scheduling sequence: where the unit sits between other packages

Integrated media storage has three gates that cannot be moved. Missing one of them turns a standard item into bespoke work at bespoke prices:

  • Coordinated drawing gate. The media wall elevation must be drawn against the electrical layout and the AV device list, not after them. Once screen size and equipment positions are frozen, carcass dimensions follow.
  • First-fix gate. Reinforcement, cable routes and back boxes are set before wall closure or tiling. This is why the unit needs to be in the materials schedule with a drawing number early: its dimensions drive the first-fix.
  • Mock-up gate. Approve one full room — screen mounted, doors operated, cables pulled, equipment running — before repeat units are released. A mock-up exposes door-swing clashes and inaccessible ports far more cheaply than a snag list does.

Repeat units: how customisation controls cost instead of adding to it

On apartment and guest-room work the practical move is to fix two or three typologies and hold them constant. Our custom and OEM service covers bespoke dimensions, internal layout, panel colours and surface finishes, so a single media unit family can be produced across different room types with the same door construction, hardware set and finish — only the widths and internals change. That keeps batch colour consistent, keeps spare parts interchangeable, and lets replacement doors be ordered later without re-matching a finish.

Where a project needs the media wall to match other joinery, schedule it together with the rest of the built-in work. The custom built-in kitchen cabinets for hotel and apartment projects line is produced under the same drawing and finish discipline, so a media unit in the living area and cabinetry in the kitchenette can come off one production batch instead of two suppliers' ranges that only look similar on paper.

One supplier for the schedule, not one per line item

The reason to put media storage, cabinetry, wardrobes and interior finishes with a single manufacturer is interface risk. A wall-mounted unit clashes with stone reveals, skirting, lighting coves and tiling setting-out far more often than it fails as a product. When the same drawing package governs all of it, dimensions are reconciled once in the factory rather than argued about on site.

Our workflow for project work runs through design consultation and space planning, material selection and product specification, manufacturing with quality control, project management and site coordination, then installation and handover. Freight arrangements cover sea, air and rail forwarding with customs paperwork, packaging and container loading, shipment tracking and door-to-door delivery; on-site installation support includes inspection and snagging. Commercial terms — Incoterms, duties, insurance, transit routing, warranty scope and response arrangements — are agreed per project rather than quoted as a blanket guarantee.

Checklist: media storage before you lock the materials schedule

  • Add integrated media storage as its own line item with a drawing reference, unit count per room type and lead time.
  • Freeze screen size, mounting type and equipment list before carcass dimensions are issued.
  • Name the party responsible for wall reinforcement, first-fix electrical, TV hardware and AV commissioning.
  • Specify ventilation for enclosed equipment and confirm door swing against adjacent drawers and doors.
  • Limit the scheme to two or three typologies and keep finishes and hardware identical across them.
  • Approve a full mock-up room with equipment running before releasing repeat units.
  • Order a spares allowance of doors, hinges, runners and brackets with the main delivery.

Send us your room schedule, screen and equipment list, and the wall construction you are building to. We will price integrated media storage — floating or built-in, sized to your elevations, matched to your joinery finishes — together with the rest of the interior fixtures, delivered door-to-door. Browse the collection at floating TV units, see wall-hung storage options in floating shelves, or start a project enquiry at contact SANTERSON.