A high gloss lacquer finish looks flawless only when the panels arrive true, the site is ready and the fixing sequence is planned before the first crate is unloaded. Most problems reported on site — telegraphing joints, chipped edges, doors that no longer align — trace back to decisions made months earlier in procurement, not to the lacquering itself. The installation plan below follows how SANTERSON coordinates cabinetry from survey and production through to handover on villa, apartment and hospitality projects.

Rule of thumb: the installation plan is written backwards. Start with the access route and the room's finished floor level, then work back to the survey date, the production slot and the shipping window.

1. Site conditions fixed before measurement

Made-to-measure joinery can only be as accurate as the substrate it is built against. Record these items in the plan and sign them off with the site team before any drawing is released for production:

  • Finished floor level and finished wall faces, marked on site — not assumed from architectural drawings.
  • Wall flatness and squareness within the run, with the out-of-plumb allowance noted so scribing panels can be sized deliberately rather than cut on site.
  • Positions of water outlets, waste pipes, risers, switch plates and floor boxes, photographed with a tape in frame.
  • Services that must be commissioned before enclosure: extraction ducting, appliance supplies, under-cabinet lighting circuits.
  • Room humidity and curing state of wet trades. Lacquered panels should not be installed into a room that is still drying out or generating dust.

2. Drawings, specification and approvals

The plan should name the drawing package that production works from and the date each approval closes. For high gloss lacquer cabinets, specify in writing:

  • Set-out elevations with overall run dimensions, appliance recesses and clearances to adjacent finishes.
  • Door style, panel construction and the exact lacquer colour and sheen reference, confirmed against a physical sample rather than a screen proof.
  • Handle or handleless detail, hinge type, drawer runners and any integrated lighting, since these determine pre-drilling at the factory.
  • Interface details with worktops, tiling, splashback, flooring and ceiling, including who is responsible for each junction.
  • A single revision cut-off. After it, changes are recorded as variations with their cost and lead-time impact.

Where a project also needs wardrobes or media walls in the same finish, keep them on one drawing set so lacquer batches stay consistent across rooms — our High Gloss Lacquer Wardrobes are made to the same project-specific dimensions and finish schedule.

3. Delivery route, storage and unpacking

Lacquered fronts are the part most often damaged between the container and the wall. Write the route into the plan:

  • Vehicle size versus gate width, turning radius, lift capacity and lift or stair carry for upper floors.
  • A dry, covered, secure holding area at ground level, off the floor on pallets, panels upright and edged protected.
  • Delivery sequencing by room or apartment, with crate labels matched to the set-out drawing numbers so fitters never sort on site.
  • A documented inspection on arrival: check for edge chips, surface scratches and moisture damage in the packaging, photograph anything abnormal, and report it the same day.

For international shipments this stage sits inside logistics and door-to-door delivery, covering packaging, container loading, customs documentation and tracking to the project address.

4. Sequence of works on site

StageWhat the plan must fix
Pre-fit checkConfirm dimensions against site conditions; verify carcass, door and hardware packs against the packing list.
Carcass settingLevelling method, fixing type per wall build-up, and the order of runs so a mistake is not carried into the next unit.
Worktop templatingWho templates, when, and how cut-outs for sinks and hobs are coordinated with the appliance schedule.
Lacquer front fittingLast possible step, after wet trades and dust-generating works are complete; gloves required; protective film removed only at handover.
Adjustment and alignmentDoor gap and reveal tolerance agreed in advance, checked run by run rather than all at the end.
Snag list and handoverNamed parties, a fixed review date and a written sign-off record.

5. Responsibilities, access and protection

  • Named site contact for the fitters, with agreed working hours and a lockable work area.
  • Floor and threshold protection along the carry route, plus protection for installed units during later trades.
  • Clear split of duties between our installers and local trades for plumbing, electrical connections and making good.
  • Waste removal arrangements, including packaging, which arrives in volume on a multi-apartment job.

Where the same supplier handles several trades, this coordination is part of installation and after-sales support: on-site fitting, inspection with a snag list, and spare parts for later replacement.

6. Cleaning, care and handover documents

High gloss surfaces show every smear during construction, so the plan should state explicitly that aggressive cleaners, abrasive pads and solvent-based adhesives stay away from the fronts until handover. Issue with the completed installation:

  • A care sheet for the lacquered surfaces: soft cloth, mild detergent, no scraping at the edges.
  • Hardware specification and adjustment notes, so alignment can be corrected without removing doors.
  • As-built record of final dimensions and finish references, useful when matching future additions.
  • Spare-parts contact details and the warranty terms actually applicable to the project.

7. Common gaps that delay handover

  • Survey taken before the screed or plaster skim was finished, so the run is a few millimetres out on arrival.
  • Finish approved from a photograph instead of a sample, producing fronts that read differently under site lighting.
  • Appliance dimensions never confirmed, discovered only at worktop templating.
  • No storage area agreed, leaving lacquered crates in an open yard for days.
  • Fronts fitted early to "check the look", then damaged by painters and tilers working behind them.

Every one of these is a planning item, not a workmanship failure — and each costs less resolved on paper than on site.