A materials schedule that lists wardrobes as one line item is where most bedroom joinery errors begin. Wall mounted open wardrobes sit between three trades - the wall they hang on, the floor finish below them and the lighting or ceiling detail above them - so they need their own row, their own dimension set and their own sign-off stage. Below is how we place them in a whole-project schedule, from the first space-planning drawing to handover.
Why this item needs its own line in the schedule
Open wardrobes have no door assembly to hide behind. Shelf spans, hanging rail heights, back panel type and the fixing method all become visible decisions that the client sees on site. On a villa or apartment package, one run of wall mounted open wardrobes normally touches four separate packages:
- Wall substrate and finishes. Stud positions, noggins and any wall panel or plasterboard build-up must be set before the fixing detail is drawn.
- Floor levels. Threshold heights and floor build-up determine where a base rail or drawer unit can sit without fouling the finish.
- Lighting. Recessed spots, wall sconces and any integrated cabinet lighting need cable routes agreed with the carcass depth.
- Ceiling and cornice lines. Full-height runs meet the ceiling detail, so the two drawings have to carry the same level datum.
If the schedule shows wardrobes as "built-in furniture, by others", none of those four interfaces has an owner. Give each run its own row with a drawing reference and a responsible party.
The fields we put in every wardrobe row
Our schedule template keeps the same columns for joinery as it does for tiles, doors and lighting, so quantities and procurement dates stay comparable across packages. For each open wardrobe run we record:
| Field | What it controls |
|---|---|
| Room / zone reference | Ties the item to one room schedule, so two identical bedrooms do not share a single line. |
| Product and collection | Names the exact catalogue item or custom equivalent, e.g. minimalist open wardrobes for a clean-lined scheme. |
| Made-to-measure dimensions | Width, height and depth taken from the setting-out drawing, not the catalogue default. |
| Material and finish code | Board material, surface finish and edge treatment, matched to the finishes schedule for that floor. |
| Internal layout | Hanging rail heights, shelf counts and spans, drawer or basket positions, lighting provisions. |
| Fixing and substrate note | Wall type, reinforcement position and the load path for the hanging system. |
| Interface owner | Who signs off wall set-out, floor levels and electrical routes before production starts. |
| Approval and lead time | Date of shop-drawing approval and the matching production window. |
Setting out the item in three stages
Stage 1 - Space planning and layout
At concept stage we fix the run length, the room it belongs to and whether the unit is wall mounted, freestanding or a combination. This is also where open storage gets tested against daily use: hanging heights for long garments, shelf depth for folded items and clear floor space for movement. A layout agreed here prevents change orders later.
Stage 2 - Shop drawings and specification
Once dimensions are taken from site, we issue shop drawings showing each elevation with the internal layout, finish code and fixing detail. Because these units are made to measure, material and finish options are specified per project rather than chosen from a fixed list. The client signs this drawing; it becomes the procurement reference for that row.
Stage 3 - Production, delivery and installation
Production starts only after the wall substrate, floor levels and electrical routes are confirmed on site. As part of our turnkey scope, the approved units move through manufacturing, quality checks and door-to-door delivery to the project address, then installation and snag inspection with the rest of the joinery package.
Schedule rule we apply: no open wardrobe row goes to production until the wall set-out drawing, floor level record and electrical route drawing for that room are all signed. One unsigned interface is enough to hold up the whole bedroom package.
Keeping it consistent with the rest of the fit-out
Open wardrobes read best when their finish language matches adjacent joinery - the same veneer, lacquer or melamine used on wood tone open wardrobes, vanity fronts and tall cabinets in the same room. We therefore cross-reference the wardrobe row against the finishes schedule and the interior doors schedule, so a change to one is visible in the others before it reaches production.
A short checklist before sign-off
- Does every room with built-in storage have its own wardrobe row, not a shared line?
- Is the fixing method stated for each wall type in that run?
- Are shelf spans and hanging heights drawn, not just implied by a layout sketch?
- Is the finish code matched to the finishes schedule for the same floor?
- Are lighting provisions and cable routes shown on the same elevation?
- Is one named party responsible for each of the four interfaces above?
Next step
If you are assembling a materials schedule for a villa, apartment or hospitality package and want the joinery rows drafted to this standard, send us the room drawings and we will return wardrobe elevations, dimensions and finish options for each run. Our team handles design coordination, made-to-measure production, delivery and installation as one scope, so the wardrobe line keeps a single owner from drawing to handover.