A materials schedule that carries every line item except one. That one is the wardrobe tucked into the bedroom angle, specified late, priced late and built late. Sliding door corner wardrobes sit at exactly that intersection of joinery, hardware and floor plan, so they belong in the whole-project schedule from the first coordination meeting, not in a variation order six weeks before handover.

Why the corner unit is the one that slips

Straight runs of cabinetry are easy to schedule because they behave predictably: a length, a height, a finish. A corner wardrobe does not. Two walls meet at an angle that is rarely perfect, the return leg has to clear doors and skirtings, and a sliding door needs a track zone that no other element in the room may occupy. When these items are scheduled separately from the rest of the fit-out, each supplier works from a different drawing set and the conflicts surface on site.

Our Sliding Door Corner Wardrobes are made to measure for each project, with the layout, dimensions and finish specified against the actual room rather than a standard module. That flexibility only pays off if the unit is in the schedule early enough for those measurements to be taken from a settled wall setting-out.

Put it in the schedule as one line, not four

The practical mistake is splitting the item across trades: carcass with one package, doors with another, track and runners with a third. Each line looks complete on paper and together they produce gaps. Write the corner wardrobe as a single scheduled item that names everything it depends on.

Schedule fieldWhat to record for a sliding door corner wardrobe
Location and room referenceRoom number plus the two bounding walls, so the return leg is unambiguous on plan.
Set-out statusWhether wall lengths and floor level have been surveyed from the built condition or are still taken from drawing.
Door type and track zoneSliding configuration, overlap dimension and the clear floor run the door needs to travel.
Adjacent finishesFlooring, skirting, wall panel and cornice lines that the carcass must meet or scribe to.
Interior layoutHanging heights, shelf runs, drawer banks and any lighting provision inside the unit.
Finish referenceThe finish code used across the project, so the wardrobe matches other built-in furniture in the same package.
Lead time and release dateDate the surveyed dimensions are released to production, working back from the installation window.

Coordinate the interfaces before you release for manufacture

Three interfaces cause most of the rework on this item, and all three are schedulable if you decide them at coordination stage.

  • Flooring first or wardrobe first. Decide which is installed before the other and record it. A made-to-measure carcass measured over the finished floor sits differently from one under which flooring runs, and that decision changes the quoted height.
  • The track run. Sliding doors travel along a fixed path. Confirm that nothing in the room layout - bed, wardrobe return, doorway swing, radiator or wall light - crosses it, and mark the run on the reflected ceiling plan as well as the floor plan.
  • The corner return. The leg that turns into the second wall has to clear whatever is on that wall. Where several rooms share a repeated layout, check each opening individually rather than assuming the corners are identical.

Where the bedroom opens onto a dressing area, the same logic extends further. L Shaped Corner Wardrobes and Glass Sliding Door Wardrobes usually appear in the same villa or apartment package, so schedule them together and let one supplier carry the whole wardrobe group. Consistent carcass construction, matching hardware and one inspection point at handover are worth more than three separate awards.

Specify the finish against the project, not the catalogue

Wardrobe doors are large flat surfaces in a room where other joinery is already specified: kitchen fronts, vanity units, doors and wall panelling. A finish picked from a small sample card can read differently across a full-height sliding panel under bedroom lighting. Take the finish decision from a project-level board that shows wardrobe, cabinetry and door together, and record the reference in the schedule so substitutions are visible rather than silent.

Because these units are produced as made-to-measure work with selectable materials and finishes, the specification in your schedule is what governs. Vague entries such as "wardrobe to match" produce exactly the mismatch they were meant to avoid.

Where the item sits in a turnkey package

For villa, apartment and hospitality projects we supply built-in furniture alongside the rest of the fit-out through our Turnkey Solutions, from space planning and material selection through production, door-to-door delivery and installation. Scheduling wardrobe, cabinetry and interior fixtures with one supplier means one drawing review, one set of surveyed dimensions and one release date to track.

If you are assembling a materials schedule now, send the room drawings together with your target installation window and we will return a scheduled entry for the corner wardrobes - layout, finish reference and release date included - rather than a price with no dates attached. As a China-based furniture and building materials manufacturer, we work from your schedule format so the wardrobe line lands in the same column as everything else. If you are handling furniture sourcing for Australian projects, that single-column discipline is where a built-in item stops being a variation order.

Before you release any corner wardrobe for manufacture: dimensions surveyed from the built condition, track run confirmed clear on both plans, finish reference taken from a project board, and the flooring sequence written down. Four lines in the schedule, and the item stops being the one that slips.

Working up a whole-project materials schedule for a villa, apartment or hospitality development? Send us your drawings and we will price and schedule the wardrobe package with it.