A swim spa is easy to leave out of a materials schedule. It sits between landscaping, civil works and MEP, so it slips past the interior package and past the structural package, and by the time somebody notices it, the slab is poured and the electrical board is fixed. If your project includes the Outdoor Swim Spa WS-PC04CH, treat it as a line item with dependencies, exactly like a joinery run or a batch of sanitaryware. The notes below follow the way we schedule the rest of a villa or hospitality package: scope first, then interfaces, then long-lead procurement.
Why swim spas break out of the usual furniture schedule
Most of what we supply for a project arrives as loose furniture, built-in cabinetry or finish material. A swim spa is different on three counts. It needs a prepared base and usually a pit, trench or plant recess. It needs a dedicated power feed, protection device and an earthing arrangement designed by the project engineer. And it needs access: a fabricated shell arriving in one piece has a turning radius on site that nobody can change after the boundary walls go up.
None of these are problems if the item is scheduled early. All three become expensive if the item appears for the first time at tender stage, when the wet trades have already been priced.
The specification line to put in the schedule
Write the entry the same way you write any other fixture line: model, quantity, dimensions, performance items and options. For this model, the catalogue entry we publish reads as follows.
| Schedule field | Catalogue entry for WS-PC04CH |
|---|---|
| Model | WS-PC04CH |
| Overall dimensions | 4500 x 3000 x 900 mm (L x W x H) |
| Total power | 2.45 kW |
| Jet total | 46 pcs |
| Water pump / filter pump | 1 pc each |
| Control system | 1 set |
| LED lights | 1 pc |
| Features shown | Water jets, LED lighting, ozone |
| Swim training system | Not listed for this catalogue entry - confirm before ordering if the design assumes one |
Those figures come from our published catalogue page. Use them for coordination and quantity take-off, then issue them back to us as a proposed configuration and ask for a confirmed specification sheet against your project. Equipment included in the price and the electrical requirements both move with the selected options.
Interfaces to name in the schedule
A single line item hides four separate responsibilities. Put each one in the schedule with a party against it, otherwise the interfaces fall between contracts.
- Structure and groundworks. The prepared base, any pit or perimeter trench, drainage falls and the load path for a full shell. Confirm who sets out the base level and to which datum.
- Electrical. A dedicated circuit sized for the confirmed total power, plus the protective device, RCD arrangement and bonding. The 2.45 kW figure in the catalogue is a starting point for the electrical designer, not a final load.
- Plant and access route. Where the pumps, filter pump and control system sit, how they are reached for servicing, and how the shell itself gets to that position on site.
- Finishes around the spa. Decking, coping, poolside paving and any outdoor furniture or shading structure placed near it. These need the same level and setting-out drawing as the spa rim.
Options that change the price line and the drawings
Catalogue options for this range include control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation and steps. Each one has a consequence beyond the purchase order:
- A heat pump adds connected load and often an outdoor equipment position with noise and clearance considerations.
- Insulation changes the shell build-up and affects running energy use in cooler months.
- Sand filtration needs a plant position, access for media changes and drainage.
- Steps change the internal layout and the rim detail where they meet the coping.
- UV sterilisation adds a small electrical point at the plant.
Decide these before you request pricing. A quotation taken on the base configuration and then amended after the drawings are issued costs more than an hour of design time, and it restarts the electrical coordination.
Where it sits in a whole-project package
Projects that buy the spa inside a wider package rather than as a standalone purchase get two practical benefits. Setting-out information travels with the rest of the drawings, so the pool rim, the deck levels and the joinery or bathroom thresholds are resolved on one set of sheets instead of three. And delivery is sequenced with everything else: the shell, bathroom fixtures, lighting and window coverings arrive in a planned order rather than competing for crane time and storage.
As a one-stop furniture and building materials supplier, we schedule swim spa items the same way we schedule the rest of the package: specification confirmation, production slot, packing list with container loading plan, then delivery to site. The custom and OEM service covers finish and configuration choices where the standard catalogue entry does not match the design intent.
Lead time and sequence on a real programme
Work backwards from the wet trades, not from handover. A reasonable sequence looks like this:
- Concept / design development: confirm model, dimensions and option set. Freeze the position on plan.
- Documentation: issue confirmed specification to the structural and electrical designers; agree base detail, trench, power feed and plant position.
- Procurement: place the order once the configuration is signed off, so the production slot sits inside your programme rather than after it.
- Groundworks window: base, drainage and conduit sleeves completed before the shell can be set.
- Delivery and setting: shell placed with the access route still available; connection and commissioning follow the electrical first fix.
The item most often missed is the sleeve or conduit run under the base. It costs almost nothing while the slab is open and a saw-cut job once it is cured.
A short checklist for the scheduler
- Model number written in full, with the catalogue link or specification sheet reference.
- Dimensions and total power carried into the structural and electrical drawings, not just the purchase order.
- Option list confirmed and priced before drawings are issued for construction.
- Named party against each interface: base, drainage, power, plant access, coping and decking.
- Access route and crane or lift plan noted on the delivery line.
- Commissioning and handover included as a programme activity, with the control system documented for the facilities team.