A slim frame French door looks simple on a drawing: two leaves, narrow sightlines, full-height glass. In practice it is one of the most coordination-heavy items in a villa or hotel fit-out, because the frame, the opening, the hardware and the floor threshold all have to agree before production starts. The checklist below follows the order we work in on residential and hospitality projects, from the opening itself through to delivery and fixing, so nothing gets decided twice.
1. The opening: what has to be frozen before you specify the door
Slim frames leave very little room for correction. With a wide timber casing you can absorb an out-of-plumb reveal; with a narrow metal or thin-profile frame, every millimetre shows. Before any measurement is taken, confirm that the wall build-up is finished and settled.
- Structural opening dimensions — width, height and wall thickness, measured at several points, not from the drawing alone.
- Plumb, level and square — record the deviation. A lean of a few millimetres changes the frame detail and sometimes the leaf layout.
- Finished floor levels — the door is set out against the completed floor, not the screed. Note the floor build-up depth and any underfloor heating.
- Reveal and lining detail — decide whether the frame sits flush with the wall face, recessed, or aligned to one side, and who supplies the architrave or architrave-free detail.
- Adjacent finishes — plaster, stone, tile or timber returns that the frame has to meet, including movement joints.
2. Leaf layout, glazing and sightlines
Once the opening is fixed, the visual decisions follow. This is where a modern slim frame French door differs from a traditional one: the proportion of glass to frame becomes the design feature, so the mullion position and glazing bar layout must be drawn rather than assumed.
- Leaf width and active/passive order — which leaf carries the handle and lock, which is the follower, and which direction each swings.
- Astragal and meeting stile detail — rebate, flush, or overlapping seal; this decides weather performance and how the leaves close.
- Glazing type — single glazed, double glazed units, laminated for safety, or patterned and reeded glass where privacy matters. Glazing thickness drives the glazing bead and the frame depth.
- Transoms and arched heads — if the opening has an arch or fanlight, confirm whether it is one unit or a door with a separate fixed light above.
- Sightline symmetry — check that the vertical mullions line up across a run of doors and windows, especially where internal and external joinery meet.
3. Hardware: specify it with the frame, not after it
Hardware is the item most often left too late. Slim stiles cannot always accept a standard lock body, and surface-mounted pulls compete with the clean edge you paid for. Decide the following at specification stage:
| Item | What to confirm |
|---|---|
| Hinges | Concealed or surface-mounted, load rating per leaf, finish, and whether the frame profile can host the hinge pocket. |
| Lock and keep | Mortise sash lock on the active leaf, flush bolt on the passive leaf, plus keying or cylinder type for external doors. |
| Handles and pulls | Projection, fixings through the frame, and coordination with any door stop or floor spring. |
| Threshold and drainage | Sill profile, drip detail, and how the threshold meets the finished floor and any drainage channel. |
| Hold-open and closers | Floor springs, wall closers or magnetic hold-fasts, including access requirements for maintenance. |
| Restrictors | Child safety, wind loading and maximum opening angle where the door opens onto a balcony or terrace. |
4. Materials, finish and matching the rest of the joinery
Doors rarely stand alone. In a whole-house project they have to match wardrobes, panelling, sliding systems and skirting in colour, grain direction and sheen. Our decorative interior doors are specified this way: the finish is chosen against the joinery package, not from a single sample card.
- Substrate and stability — solid timber, engineered core or metal frame; how each behaves with heating, humidity and large glazed areas.
- Finish system — painted, veneered, laminated or metallic; edge banding and profile breaks are where a cheap finish is spotted first.
- Hardware finish match — hinges, handles and tracks in the same tone as ironmongery elsewhere in the project.
- Spare leaves and panels — order matching spares with the original batch to avoid later colour mismatch.
5. Verification drawings and sign-off
For a project of any size, ask for shop drawings before production and check them against the site survey. A single round of mark-ups on paper costs nothing; a door recast after manufacture costs weeks.
- Cross-check every dimension on the drawing against the site record, not the architectural schedule.
- Confirm leaf layout, hinge hand and opening direction on the plan view, with the drawing oriented as it will be installed.
- Confirm glazing thickness, glass make-up and any safety or laminated requirement per location.
- Confirm hardware schedule: item codes, finishes, quantities and keying arrangement.
- Get written sign-off from the designer or site lead before manufacture is released.
6. Packaging, delivery sequence and fixing
Glazed slim-frame doors are fragile and heavy, and they usually arrive with the rest of the joinery package. Sequencing matters more than people expect: a door delivered before the decoration is complete sits in a corridor for six weeks and gets damaged.
- Pack vertically with edge protection and glazed-unit bracing; label each set by room or opening number.
- Deliver to a dry, secure store with access for two people and lifting equipment where the leaves are large.
- Fix after wet trades and floor finishes are complete, then adjust and hang on the final floor level.
- Run a snag list per opening: closing, locking, seal compression, glass condition, finish damage.
7. Commercial terms to lock down in the quotation
- What is included: frame, leaves, glazing, ironmongery, architraves, threshold, sealants and fixings.
- What is excluded: on-site making good, structural alterations, and any local installer input.
- Lead time measured from drawing approval, not from order date.
- Packaging, freight mode and delivery terms to site, plus who handles customs clearance.
- Spares policy and how replacement leaves or hardware are ordered later.
How a supplier handles the whole checklist in one package
When doors, wall panelling, wardrobes and flooring come from separate sources, the details between them — architraves, thresholds, floor levels, finish matching — become the contractor's problem. Under our turnkey villa furnishing service the same team handles space planning, production coordination and on-site guidance, so opening details are agreed across trades before manufacture starts. As part of a one-stop furniture and building materials supplier scope, we also cover freight by sea, air or rail with the shipping paperwork, followed by installation support and after-sales service.
Quick pre-production checklist
- Opening surveyed after wall build-up and finished floor levels are set
- Leaf layout, hinge hand and swing direction confirmed on plan
- Glazing make-up and thickness agreed with the frame profile
- Full ironmongery schedule including keying and threshold
- Finish matched to the wider joinery package, spares ordered in the same batch
- Verification drawings signed off before manufacture release
- Delivery sequenced after wet trades, with a per-opening snag list