A swim spa shell arriving on site is only half of the job. The difference between a clean handover and a long list of site problems is the installation plan written before the container is booked. Using the Outdoor Swim Spa WS-PC02 as the worked example, this guide sets out what a complete installation plan should contain, so the buyer, the site contractor and the supplier are working from the same document.
1. A confirmed specification sheet, not a model number
The plan starts with a signed configuration sheet. The catalogue page for WS-PC02 lists this model at 3000 x 3000 x 1050 mm, with one control system, two water pumps, one filter pump, sixty jets, one LED light and a total power figure of 7.35 kW, together with water jets, LED lighting and ozone as the shown features. Treat those figures as the catalogue baseline for this model. Options such as a heat pump, UV sterilisation, sand filtration, extra insulation and steps change both the equipment list and the services that feed the unit, so the plan must reference the exact configuration ordered rather than the model code alone.
Baseline from the WS-PC02 catalogue page
Footprint: 3000 x 3000 mm, Depth: 1050 mm
Water pumps: 2, Filter pump: 1, Jets: 60, LED lights: 1, Control system: 1 set
Total power: 7.35 kW, Shown features: water jets, LED lighting, ozone
Optional items listed in the catalogue: control systems, UV sterilisation, water pumps, heat pumps, sand filtration, insulation, steps
2. Site access, foundation and drainage
Before any concrete is poured, walk the delivery route and the installation route. The plan should record the dimensions of gates, side passages, stairwells or lifts between the kerb and the final position, plus a note on whether a crane, a tail-lift or manual handling is needed. A 3000 x 3000 mm shell needs more clearance than its footprint suggests, because it cannot be tilted through tight corners.
- Foundation type and load rating, confirmed by the local structural engineer for the soil and the filled weight of the spa.
- A level, fully supported base. Note whether the shell sits on a slab, a raised deck with a cut-out, or a partially recessed pit, and who is responsible for each.
- Clearance for the equipment compartment and for future service access to the pumps, filter and control system.
- Drainage away from the base, and an overflow path for backwash water from the filter pump.
- Distance from the house, boundary and glazing, so splash-out and plant noise are managed at design stage rather than after handover.
3. Electrical design signed off by a licensed electrician
Electrical work is where installation plans most often fail, because the supplier's data sheet and the local wiring rules are handled by different people. The plan must state the confirmed supply arrangement for the ordered configuration: circuit rating, dedicated final circuit, protective device type, earthing and bonding arrangement, and the location of the isolator out of wet reach but within reach of an operator.
The catalogue total power figure is a planning input, not an electrical design. The electrician sizes the circuit from the actual installed equipment, including any heat pump or extra pumps added to the configuration, and applies the requirements that apply at the site. Record in the plan who supplies the cable to the spa, who terminates it, and who tests and certifies the installation.
Electrical items to close out before ordering
Confirmed equipment list including heat pump or added pumps; supply voltage and phase; dedicated circuit and protective device; bonding to all metal parts; isolator position; test and certification responsibility.
4. Water supply, filling and first startup
Specify where the fill line comes from, whether a permanent tap or a temporary connection is used, and how the water chemistry baseline is set before the spa is handed over. The plan should cover the filter pump run time for initial circulation, the ozone system's commissioning point, and the sequence for filling in stages so the shell is never empty on a hot day or overstressed while it settles.
- Fill source, hose route, and who pays for the water.
- Chemical dosing method and storage location for the chosen sanitisation setup.
- A commissioning checklist: pumps, each jet circuit, LED lighting, ozone, control system response.
- A named witness for startup, with readings recorded on a single sheet that becomes part of the handover file.
5. Delivery, packaging and container plan
For an imported unit the plan should match the logistics document to the site reality: container type, offload method, delivery date window, and who provides the lifting equipment on the day. Packaging must be listed so the site team knows what to keep until the spa is positioned and inspected; damage claims are far harder to raise once the crating is cleared.
Our logistics and door-to-door delivery service covers freight forwarding, customs paperwork, packaging and container loading, shipment tracking and delivery to the site address. The installation plan should still name the local offload and handling steps, because those sit with the buyer's contractor.
6. Responsibilities, sequence and handover
A one-page responsibility matrix prevents most disputes: supplier for the shell, equipment and configuration; local builder for base, waterproofing and finishes; local electrician for supply, protection and certification; both parties for commissioning and snag inspection. Then set the sequence with hold points, so no trade starts before the previous item is signed off.
Our installation and after-sales support includes on-site installation, inspection and snag lists, warranty coverage, spare parts and ongoing maintenance. Response times and warranty terms vary by project, so the plan should record exactly what applies to your order rather than assuming a standard package.
- Snag list template attached to the plan, with photo evidence for each item.
- Spare parts held on site or nearby: jet inserts, seals, filter element, LED module.
- Owner's manual, wiring record and commissioning sheet handed over together, not separately.
- A named contact at each party for the warranty period.
7. Documentation to keep with the plan
The final section of the plan is simply a list of what must exist at handover: the confirmed configuration sheet, foundation sign-off, electrical certificate, commissioning readings, warranty terms, and the as-built layout drawing showing spa position, clearances and equipment compartment access. If any of these are missing, the installation is not finished, whatever the site looks like.
If you are specifying a swim spa for a villa or resort project, send us the site drawings and the configuration you want. We will confirm the equipment list, power and clearance requirements for that configuration before production starts, through our project services.