A metal-frame modular wall system looks simple on a rendering: uprights, brackets, shelves, maybe some integrated lighting and closed modules in between. On site it is one of the least forgiving products to install, because every deviation in the wall, the floor level or the ceiling height shows up as a crooked shelf line or a gap that cannot be closed. The installation plan is where those problems get solved on paper instead of on site. Below is what we ask project teams to settle before Santerson Metal Frame Modular Systems enter production, and what a complete plan should hand to the crew that finally fixes the system to the wall.
Why modular systems need a plan rather than a shop drawing
Modular shelving is made to measure. The frames, shelf depths and finish options are specified per opening, so the production file and the site condition have to agree exactly. Unlike a freestanding cabinet that can be shimmed into plumb, a wall-anchored frame system transfers its tolerances to the building: if the setting-out drawing is wrong by 15 mm, the whole bay shifts, and door openings, skirting returns or light switches end up in the wrong place.
An installation plan is also the coordination document. Modular walls rarely stand alone. They meet integrated lighting, power and data runs, plasterboard or timber battens that have to carry the load, and sometimes joinery from another trade. The plan is where those interfaces are drawn once, instead of being argued about on the day.
1. Verified site dimensions and a datum line
Before anything else, the plan records measured dimensions taken on site, not dimensions read off architectural drawings. For each wall run, note:
- Floor-to-ceiling height at several points along the run, since slabs and ceilings are rarely level across a long span.
- Plumb and bow of the wall face, with the largest deviation marked at its location.
- Positions of finished floor levels, skirting, architraves, switches, sockets, radiators and any recess.
- Clear opening width at both ends of the run, in case the wall tapers.
From these measurements the plan sets one datum line — a horizontal reference from which every upright, bracket row and shelf height is dimensioned. A floor-to-ceiling configuration in particular needs this: floor-to-ceiling systems bear against both surfaces, so the plan must state the packing or scribing allowance at the head and the sill rather than assuming a single nominal height.
2. Substrate, fixing method and load duty
The frame only performs as well as what it is bolted to. The plan should state, for each run, what the substrate is and how the fixings are chosen for it:
| Substrate condition | What the plan must specify |
|---|---|
| Solid masonry or concrete | Anchor type and embedment depth, drilling sequence, and whether the frame sits on a batten or directly on the face. |
| Plasterboard or drywall only | Position of studs or noggins, or a designed backing/batten framework that carries the load back to structure. |
| Timber or steel stud partition | Line and location of continuous backing timber, plus fixing centres matching the frame grid. |
| Uneven or out-of-plumb wall | Shimming or framed-out packing zones, with the maximum packer thickness allowed at each position. |
Next to the fixing note, list the intended load duty for each bay: books and display objects, glass shelving, a television, closed modules loaded with linen, or a combination. This is what determines bracket spacing and shelf depth, and it should be agreed with the client before production rather than discovered after handover.
3. Configuration schedule and finish breakdown
A single elevation drawing is not enough for a mixed run. The plan carries a configuration schedule that numbers every module — open shelf bay, closed cabinet, display niche, TV or media panel, drawer unit — and records for each item the width, height, depth, shelf count and finish code. Finish codes matter more than they appear: metal frame colour, shelf laminate or veneer, and glass type are ordered separately, and a mismatch between the schedule and the purchase order is one of the most common causes of delay.
The schedule should also flag where field adjustments are expected. Scribed end panels, cut-to-size fillers at ceiling junctions, and returns around columns belong in the plan as named line items so they arrive with the shipment instead of being fabricated on site with hand tools.
4. Services, lighting and electrical coordination
Integrated lighting is where modular systems most often stall the programme. For every lit bay, the plan states:
- Where the driver or transformer sits, and that it stays accessible for maintenance.
- The cable route from the supply point to each frame channel, and who pulls that cable — electrician or joinery crew.
- Switch location, dimming method, and whether the control is wall-mounted or integrated into the system.
- Voltage and lamp specification, confirmed against the selected profile before the frames are drilled or punched.
The same discipline applies to sockets and data outlets inside the run. Cutting a shelf to take a socket after installation is destructive work; cutting the opening in the factory is routine. The plan decides this in advance.
5. Sequencing, access and delivery
Modular frames are long, and finishes are easily damaged. The installation plan should fix the sequence: framing and backing first, then electrical rough-in, then a wall-closure inspection, then system installation last, after painting, flooring and ceiling work are complete. Where that order cannot hold — for example on a fast-track villa fit-out — the plan says how installed frames will be protected and who is responsible for touch-up.
Logistics belong in the same document. Record the delivery route from the truck to the room: lift dimensions, corridor widths, stair turns, and whether panels need to be crated vertically. For overseas shipments, confirm that the packing list matches the configuration schedule module number by module number, so a missing piece is identified on the day the container is opened rather than three weeks later.
6. Responsibility matrix and sign-off
The clearest plans end with a short table naming who does what, and when. A typical split for an imported modular system:
| Task | Typically the supplier | Typically the local contractor |
|---|---|---|
| Site survey and measured drawings | Review and approval of dimensions supplied by site | Taking and submitting measurements |
| Backing framework and wall preparation | Provide fixing detail and load duty | Build to the stated detail |
| Electrical first fix and testing | Provide lighting layout and cable schedule | Execute and test circuits |
| System installation | Supervision or install crew, per contract scope | Site access, set-out assistance |
| Snag list and handover | Replacement parts for defects | Punch-list closure on site |
Add a sign-off line: the date the setting-out drawing was approved, the date the configuration schedule was frozen, and the name of the person who signed each. Once those two dates exist, later changes are treated as variations instead of corrections, which protects both sides of the contract.
7. Handover documentation
What should reach the client at completion is more than a clean wall: an as-built configuration schedule with the final module numbering, the finish codes actually applied, the lighting specification with driver details, fixing and load-duty notes for anyone reorganising the system later, and spare-part references for shelf brackets and panels. This is what makes the system maintainable ten years on, when a shelf needs replacing and nobody remembers which code was used.
A practical check before production: if the plan cannot answer all five questions — where is the datum line, what is the substrate, what carries the load, where does the lighting cable terminate, and who signs off the setting out — it is not yet an installation plan. It is a drawing with good intentions.
How Santerson supports this stage
As a one-stop furniture and building materials supplier, we work with project teams from the survey stage through to installation: made-to-measure sizing and finish selection for metal-frame modular systems, coordinated production of shelving, closed modules and integrated lighting in one shipment, and door-to-door delivery to villa, hospitality and office projects. Our custom & OEM service covers bespoke dimensions, materials and finishes, while the installation and after-sales stage covers on-site guidance, snag inspection and replacement parts.
Send us your elevation drawings and measured dimensions, and we will return a configuration schedule with fixing details, load-duty notes and a lighting layout you can put straight into a coordination meeting. That document is the difference between an installation day that runs to plan and one spent cutting fillers on the kitchen floor.
Planning a modular wall system for a villa or hotel project?
Contact PHILLIP at SANTERSON — Phone / WhatsApp +86-13928214007, email santerson@qq.com — to review your setting-out drawings and configuration before production starts.