A materials schedule is the document that keeps a villa or hospitality fit-out from drifting. It lists every finish, who supplies it, what size it has to be and when it arrives on site. Wall panels look like a small line in that list until they clash with joinery, lighting or door openings. This guide shows how our Santerson Glass & Glossy Panels are specified and scheduled so that reflective wall surfaces arrive measured, coordinated and ready to install alongside the rest of the package.

What a materials schedule actually has to carry

Across a whole-project package, from cabinetry and doors to wall finishes and loose furniture, the schedule is not a shopping list. Each line item needs enough information that procurement, factory and site team all read the same instruction. For a wall panel that means the finish reference, the panel size and thickness, the substrate and fixing method, the edge and trim detail where panels meet other materials, and the room or elevation the panel belongs to. A row that only says "glossy panel, feature wall" will come back as a question, and every question is a day off the programme.

We work as a furniture and building materials manufacturer, so panels are usually quoted in the same package as cabinetry, doors, vanities and loose furniture. That is where the coordination advantage sits: one team sees the wardrobe carcass, the sliding panel track and the feature wall on the same drawing set, instead of three suppliers reconciling after the fact.

Reading the product before you schedule it

Glass & Glossy Panels belong to our Paneling Systems collection. The published description covers configurable glass and glossy panels for residential wall system projects, with finish, layout and dimensions specified per space, made-to-measure sizing, and material and finish options to choose from. Two things follow directly from that wording, and both matter for the schedule:

  • The panel is not a stock size. Dimensions are made to measure, so the schedule must carry measured openings and setting-out dimensions, not a nominal board count.
  • Finish and material are selected, not assumed. Each configuration needs the finish reference written against the elevation it applies to, and materials, dimensions and technical performance for the chosen configuration have to be confirmed project by project before order.

That is why we do not publish a single spec sheet and ask buyers to fit the room to it. The panel is built around the drawing.

Step 1: place panels on elevations, not in a room list

Schedule panels by elevation. A living room with a TV wall, a hallway return and a head wall needs three separate rows, because each has different penetrations, different junctions and often a different finish. For each row we ask the project team to confirm:

  • The elevation reference from the drawing set, matching the number used on the joinery drawings.
  • Floor-to-ceiling or partial height, with the actual finished floor level if screed or flooring build-up is still being decided.
  • Every penetration on that wall: switches, sockets, TV bracket fixings, concealed door frames, air grilles, wall lights and curtain pockets.
  • The junction detail at each edge — skirting, cornice, adjacent stone or timber, and any reveal left for a shadow gap.

Where a wall also carries a door, decide early whether the door is concealed within the panelling. Our Integrated Door & Paneling line exists for exactly this case, and it should be on the same schedule row group as the panels so the two are manufactured to one setting-out.

Step 2: choose the finish family across the project

Glossy and glass surfaces read very differently from matte and textured ones under the same lighting. Rather than specifying room by room, decide the finish family for the whole project first, then place it. Within Paneling Systems you can hold a single design language across reflective and non-reflective walls:

Panel typeWhere it usually goesSchedule note to carry
Glass & Glossy PanelsFeature walls, head walls, bar and display fronts, compact joinery facesFinish reference, glass or glossy face, edge detail, handling and protection on site
Matte Lacquer PanelsCorridors, large wall runs where glare is a problemLacquer colour reference and sheen level per elevation
Textured PanelsLobby feature walls, accent baysTexture direction and repeat, panel orientation on the drawing
Wood Veneer PanelsStudy, bedroom and media walls matched to cabinetryVeneer species, grain match sequence and which panels sit side by side
Stone & Marble PanelsBathrooms, reception walls, wet-adjacent surfacesPatterning layout and vein direction agreed from a cutting drawing
Acoustic PanelsMedia rooms, boardrooms, open-plan loungesPerformance requirement and fixing system stated separately

Write the same finish code in the panel row, the joinery row and the door row if they are meant to match. Different codes for the "same" colour is one of the most common causes of a snag list that could have been avoided on paper.

Step 3: lock dimensions after first fix, not at concept

Because sizing is made to measure, the panel order should be released only after setting-out is frozen. In practice we ask for two dimension passes:

  • Concept pass. Approximate heights and widths, enough to price the package and check that the design intent survives value engineering.
  • Site pass. Measured dimensions taken after services, screed, plasterboard and floor build-up are complete, with the penetration positions marked on site and photographed against the elevation.

For glass-faced and high-gloss faces this second pass is not optional. A 5 mm error shows up as a visible cut line or an ill-fitting trim, and unlike a matte painted surface it cannot be adjusted on site without leaving a mark.

Step 4: write the sequencing into the programme

Panels fail on schedule when they are treated as a late decorative item. Put them in the procurement sequence where they belong:

StagePanel activityDepends on
Design and planningElevation setting-out, finish family selected, junction details drawnFlooring, lighting and door selections frozen in the same schedule
Specification and quotationMade-to-measure dimensions issued, material and finish options confirmed for the chosen configurationApproved sample or finish board signed off by the client
ProductionPanels manufactured with the associated joinery in one batchFrozen setting-out; late changes restart panel manufacture
LogisticsPanels packed and loaded so reflective faces are protected and arrive on the right delivery runSite access and storage agreed before despatch
InstallationPanels fitted after wet trades, floor finish and services testing are signed offSubstrate flat, dry and fixed to the agreed setting-out

We handle logistics and door-to-door delivery, so panel rows should also carry their pack list, container or shipment reference and the delivery sequence. Glossy faces travel with edge protection and face-to-face packing; the site team needs to know that before they plan where unpacking happens.

Step 5: record the inspection points

Add three checkpoints against each panel row so handover is a confirmation rather than an argument:

  • Sample approval. Finish board or sample signed with reference code, dated, and referenced in the schedule row.
  • Dry lay or mock-up. For reflective runs, one bay installed early to check light reflection, joint width and trim detail before the full elevation is closed up.
  • Snag list at handover. Panel edges, joints, and any penetration cut recorded against the elevation reference, with spare panels listed in the same schedule for future replacement.

Schedule discipline check. If a panel row cannot answer "which elevation, which finish code, which measured size, which delivery run, who inspects it", it is not ready to be ordered. Fix the row before it reaches production.

Common schedule errors we see corrected

Panels scheduled without the flooring decision. Panel height depends on finished floor level. If engineered timber or stone is still open, the panel size is provisional and the order should not be released.

Lighting drawn after panels are set out. Wall lights and concealed strips need fixings behind the panel. Move them afterwards and you patch a glossy face.

Mixed suppliers for one wall. A sliding system from one supplier, panels from another, joinery from a third. Set-out tolerances differ and the junction detail becomes someone else's problem. Grouping Glass Sliding Panels with the fixed panels on the same schedule keeps one tolerance rule.

No spares line. Reflective faces are the ones most likely to be damaged during later trades. A small spare quantity noted in the schedule costs little; matching a glossy finish years later usually does not come out clean.

Bringing it together

Glass and glossy panels reward projects that specify them properly: measured to the actual opening, finished to a signed reference, sequenced after first fix and delivered with protection. Put those four things in the schedule row and the panel behaves like any other building material on site. Leave them out and it becomes the item everyone argues about at handover.

If you are assembling one package for a villa or hospitality project — panels, custom built-in kitchen cabinets, doors, vanities and loose furniture — send us the elevation drawings and we will return a schedule-ready specification with dimensions, finish references and delivery grouping for each row.

Send your elevations for a schedule-ready panel specification

Contact PHILLIP by phone or WhatsApp on +86-13928214007, email santerson@qq.com, or use the contact page. Include elevation references, measured heights and your target on-site date. Enquiries receive a response within 24 hours during business hours, Monday to Saturday, 8:00 AM to 6:00 PM (GMT+8).

Product availability, material options, dimensions and technical performance for Glass & Glossy Panels are confirmed per project configuration on request. Site installation, warranty terms and response commitments should be agreed in writing for each project.