Two tone high gloss cabinets look finished in a rendering and look finished on site only when someone has planned how the doors, carcasses, hardware and worktop reach the kitchen and in what order they go in. The sequence below follows how we run custom cabinetry at SANTERSON: specification before production, protected packing for glossy panels, staged delivery to the property, then installation and snag closure.
Why a Gloss Finish Changes the Delivery Conversation
A high gloss door is unforgiving. Every edge is visible from several viewing angles, fingerprints and dust show up under kitchen lighting, and a chipped corner on a gloss panel cannot be touched up on site the way a matte or veneer edge sometimes can. That is why we treat two tone high gloss cabinets as a delivery and handling product, not just a finish choice.
The two tone layout adds one more variable. In most schemes we build, the tall units and run of base units carry one finish while the wall units, island or pantry tower carry the second. That split is decided in the drawings, and it also decides how the shipment is organised: units with different door finishes, different panel thicknesses and different hardware sets arrive as separate bundles that the installer must be able to identify without opening everything.
Decisions That Must Be Closed Before Production Starts
Cabinetry is the trade that exposes every unresolved dimension in a kitchen, so we close these items on paper before any panel is cut:
- Final set-out dimensions taken on site. Wall lengths, floor levels, ceiling heights, and the position of waste, water supply and power outlets. Gloss doors show misalignment more clearly than textured fronts, so out-of-square walls need to be measured and recorded rather than absorbed later with scribing.
- The exact split between the two finishes. Which units are gloss, which carry the second finish, and where the transition happens between them. We confirm this against elevations, not a mood board.
- Appliance schedule. Built-in ovens, fridge columns, dishwashers and extractors set the cut-out sizes and ventilation gaps. Appliance models should be fixed before carcass sizes are locked.
- Worktop material and thickness. Stone, ceramic or compact surface worktops are measured after base units are set, so the worktop supplier and the cabinet supplier must agree who templates when.
- Hardware and opening method. Handles, integrated profiles, hinge type, soft close specification and any internal fittings such as pull-out corners or tall-unit larder mechanisms.
- Site readiness date. The date the kitchen space will be clean, dry, painted or tiled, and free of other trades. This is the date we plan the delivery against.
Our custom and OEM service covers these decisions as part of the pre-production stage, including material and finish selection for each project. For Two Tone High Gloss Cabinets, sizing is made to measure and layout is tailored to the project, so the specification sheet is the document that both sides sign off.
Packing and Container Loading for Gloss Panels
Gloss doors travel differently from matt or laminated fronts. In our loading plan we separate doors from carcasses, keep each door face protected against the next, and bundle panels by unit so that everything needed to assemble one cabinet travels together. For a two tone scheme this also keeps the two finishes apart in transit, which removes most of the sorting work at the property.
- Doors and drawer fronts are packed vertically or flat in protected stacks with edge protection, labelled by unit and elevation reference.
- Carcasses travel as pre-assembled or flat-packed boxes depending on the run length and how they stack against each other without point loading.
- Glass, mirrors and any integrated lighting are crated separately from board panels.
- Hardware kits are boxed per unit group and marked so they are not mixed into general packaging waste.
- Loading order follows the site sequence: what is installed first should come off the container first.
We arrange sea, air or rail freight with the customs paperwork that accompanies the shipment, and we work with the buyer on the delivery address, the receiving party and the unloading arrangement before the container is booked. Terms, duties and transit arrangements are confirmed project by project rather than assumed.
Delivery Sequencing Against Other Trades
The most common cause of a stalled kitchen installation is not the cabinets; it is cabinets arriving into a room that another trade has not finished. We suggest this sequence to project owners and builders:
| Stage | What happens | Who needs to be ready |
|---|---|---|
| 1. First fix signed off | Plumbing, electrical and any gas runs are in position and tested; floor levels and wall finishes complete. | Builder, M&E trades |
| 2. Site survey or dimensional confirmation | As-built dimensions checked against the drawings before final production release where the programme allows it. | Our project coordinator, site foreman |
| 3. Carcass delivery | Boxes and carcasses delivered to a dry, secure storage area near the kitchen, not dropped at the front door of an occupied property. | Receiving party on site, lifting access confirmed |
| 4. Door delivery | Gloss doors and fronts delivered when the room can be kept clean and the panels can go straight to installation. | Installers on site |
| 5. Installation | Carcasses levelled and fixed, doors hung and adjusted, drawer runners and mechanisms fitted. | Our installers or your appointed fitters |
| 6. Worktop templating and fitting | Worktops templated on the installed base runs, then fitted and sealed. | Worktop supplier, cabinet installer |
| 7. Snag list and handover | Door alignment, hinge adjustment, soft close function, edge condition and finish continuity checked room by room. | Owner or project manager with the installer |
Splitting carcass delivery from door delivery is worth the extra handling. Gloss fronts do not benefit from sitting in a dusty site environment for two weeks while tiling and decorating are finished.
Installation Checks Specific to Two Tone Gloss Fronts
When our team fits these kitchens, or when we guide a local fitter through the drawings, the inspection list is short and specific:
- Carcasses levelled and aligned along the whole run, not only at each end. A run that is level at both ends but bowed in the middle will show as a visible step between adjacent gloss doors.
- Door gaps consistent top to bottom, with the reveal between adjacent doors equal across the height of the unit.
- The transition line between the two finishes straight and continuous across tall units and adjacent runs.
- Hinges and runners adjusted so no door needs force to close and none springs open.
- Panel edges and corners inspected at the point of installation, while packaging is still available as evidence for any transit damage claim.
- Integrated lighting and internal fittings powered and tested before the room is handed over.
Our installation and after-sales support covers on-site fitting, inspection with a snag list, spare parts and replacement panels. Where the buyer appoints their own fitters, we provide drawings and remote guidance so the fixing sequence and adjustment standards match what we produced.
Documentation That Should Travel With the Shipment
- Elevations and cut sheets with each unit referenced by the same code used on the cartons.
- A packing list that matches carton labels one to one, so a missing item is identified as an item, not as "something missing".
- Finish schedule stating which units carry which of the two finishes, including door and carcass colours.
- Hardware schedule listing hinges, runners, handles and internal fittings by unit.
- Commercial documents for customs clearance prepared with the shipment.
If you want a single supplier handling design coordination, production, freight and fitting, our logistics and door-to-door delivery service covers freight forwarding, customs paperwork, container loading and delivery to the project address under one programme.
Common Coordination Failures We See on Kitchen Projects
None of these are difficult to avoid once they are named. They cost time because they are usually discovered on the installation day:
- Appliance model changed after production release. Cut-outs and ventilation gaps no longer match, and gloss doors in the tall run may need remaking.
- Floor finish decided late. A thicker floor than planned changes door-to-floor clearance along the whole base run.
- No storage area agreed for the delivery. Panels end up stacked in a hallway or garden of an occupied property, which is where edge damage happens.
- Worktop templating scheduled before carcasses are levelled. Measurements taken off an unlevelled run come back wrong.
- Two finishes ordered from separate suppliers. The transition line and door thickness then have to be reconciled on site by whoever is standing there.