A set of Santerson Partition Sliding Systems rarely travels alone. Panels, tracks, hardware and finish samples usually leave the factory in one shipment but arrive into a site that is still being measured, plastered and painted. The delivery plan therefore starts long before production: it starts when you fix the opening dimensions, choose the wall configuration and decide who receives the goods at the other end. Below is the sequence we follow on project orders, from the first drawing to the handover checklist.

What makes a partition sliding order different to ship

Sliding wall systems are made to measure. Panel heights follow floor-to-ceiling levels, and track lengths follow room spans, so the quantities on your purchase order are only as good as the site dimensions behind them. Three characteristics shape the whole delivery plan:

  • Oversized, fragile components. Full-height panels and long track sections need flat packing, edge protection and a loading sequence that keeps the heaviest items on the container floor.
  • Interdependent parts. Panels, carriers, tracks, handles and any integrated glass or acoustic infill must arrive together. A missing hardware carton holds up the whole installation, not just one door.
  • Site conditions decide the finish. Once the panels are manufactured, floor levels and ceiling heights cannot be corrected at destination without rework.

For this reason we treat delivery as part of manufacturing, not as a separate step after it. The furniture logistics and door-to-door delivery service covers freight forwarding by sea, air and rail, customs paperwork, packaging and container loading plans, shipment tracking and delivery to the project address.

Step 1: Lock dimensions and configuration before anything is quoted

Confirm the finished floor level, the finished ceiling level and the clear opening width for every run of track. Note obstructions such as skirting, cornices, air grilles and light fittings that affect panel travel. State the wall layout you want: room divider, closet front, media wall or storage wall. Our configurable ranges include Santerson Acoustic Sliding Panels where separating noise between spaces matters, and Santerson Sliding Storage Panels where the same face is used for concealed storage.

Send us the drawings even if they are still at concept stage. We check them against production tolerances and flag clashes while changes are still cheap.

Step 2: Agree finishes, hardware and opening direction on paper

Each panel line can be specified with made-to-measure sizing plus material and finish options. Settle the following in writing before production release, because a change after release means re-manufacture and a new sailing:

  • Panel face material and finish, and the sample reference you approved
  • Glass type where glass is used: clear, frosted, smoked or ribbed
  • Track type, recessed or surface mounted, and the hardware set for the panel weight
  • Number of leaves, stacking direction and the parking pocket
  • Any integrated lighting, mirror or display niche inside the wall build-up

Step 3: Choose the Incoterm and the delivery address deliberately

Decide who is doing what at the border before you compare freight costs. A quotation to a port looks cheaper than a door-to-door price, but it moves the inland haulage, customs clearance and site booking onto your team. For project orders we can arrange forwarding and prepare the destination paperwork: commercial invoice, packing list, certificate of origin and the import documents your country requires. Import duties, taxes and clearance requirements differ by destination, so confirm them with your broker or with us for your specific address.

DecisionWhat it settlesWhy it matters for sliding systems
Sea or airCost, transit window, packing standardFull-height panels suit sea freight; a small replacement leaf may justify air
Port or door deliveryWho books inland transport and clearanceOversized cartons need a suitable vehicle and a lift at the destination
Single or split shipmentContainer count and arrival datesSplitting panels from hardware risks one part arriving before the site is ready
Cargo insuranceWho carries risk in transitPanel faces and glass are the items most often claimed for

Step 4: Build the delivery window around the site programme, not the sailing date

Work backwards from your installation date. Production takes time, then the goods need a sailing or flight, then clearance and inland transport, then a receiving slot on site. Add buffer for customs queries and for the trades that must finish before panels go in: flooring, painting, skirting and ceiling set-out all sit underneath the wall system.

Practical rules we apply on project orders:

  • Order samples early enough that approval does not sit on the critical path of the main order.
  • Schedule production release only after site dimensions are signed off by the person holding the tape measure on site.
  • Book the receiving slot before the vessel arrives, and confirm dock height, turning space and whether a tail-lift or crane is needed.
  • Keep the hardware cartons labelled by wall run so the fitter can work room by room instead of unpacking everything.

Step 5: Receive, inspect and store on site properly

On arrival, check carton counts against the packing list before signing, then open a representative number of cartons and photograph any damage on the outer packaging and the panel face. Store panels flat and indoors, off the floor, away from plastering and painting works. Panel faces that sit in a damp site for weeks can distort or stain, and that is not a manufacturing fault.

Keep the packing list with the drawings. When a spare part or an additional leaf is needed later, the wall run reference on the label is what lets us match the original specification and finish batch.

Step 6: Installation and after-sales

Our service scope includes on-site installation support and inspection with a snag list. Warranty terms, response times and spare-part availability depend on the order and destination, so confirm them in writing for your project before the order is released. For an integrated fit-out we coordinate the wall system alongside cabinetry, doors and joinery under one turnkey interior project solution, so one team is accountable for measurement, production and handover rather than several suppliers pointing at each other.

A short checklist before you place the order

  • Signed-off dimensions for every track run, with finished levels noted
  • Approved finish sample reference in writing
  • Agreed Incoterm, delivery address and receiving contact
  • Insurance decision recorded on the order
  • Installation date, plus the trades that must complete before it
  • Storage plan for oversized cartons on site

Send us your drawings, opening dimensions and target installation date, and we will return a configuration proposal with packing and delivery options for your address. As a custom furniture and interior products manufacturer, we handle measurement checks, production and door-to-door logistics for villa, hospitality and office projects.