A floor standing bidet rarely fails because of the ceramic. It fails because nobody checked, before the tiles went on the wall, where the water supply would come from, how far the waste outlet sits from the finished back wall, and whether the toilet beside it is an S-trap or a P-trap unit. The Floor Standing Bidet 1038F is a freestanding ceramic bidet basin fixed to the wall at the back, sold as part of a matched sanitary suite for homes, hotels and villas. This guide sets out what a contractor, designer or procurement officer needs to send us — and what we need to confirm with you — so the 1038F lands on its fixing points the first time rather than on site in a return crate.

What the 1038F actually is, in procurement terms

The 1038F is a vitreous ceramic bidet with a freestanding body that is anchored to the wall behind it. It is not a seat attachment, and it is not a shower-toilet unit: it is a separate basin for personal hygiene, sitting next to the water closet in the way bidets conventionally do in European, Middle Eastern and higher-end Asian bathroom layouts. The curved body is shaped for comfortable use, and the glossy glaze is chosen because it resists dirt and limescale build-up, which matters when the same fixture has to be cleaned daily by housekeeping rather than once a week by an owner.

Two details in the product record decide most of the coordination work. First, the back-to-wall fixing means the finished wall face, not the structural wall, controls position — insulation, tank boxing and tiled finishes all shift that face. Second, the 1038F is designed to pair with the matching Two Piece Washdown Toilet 1038A, which is offered with both floor S-trap and wall P-trap outlets. That pairing is what makes the bidet read as part of a suite instead of an odd extra, and it also means the waste arrangement you choose for the WC has to be considered alongside the bidet waste at drawing stage.

Read your own drawings before you read our catalogue

Most coordination problems we see on hospitality and villa jobs are not product problems. They are a mismatch between three separate sets of drawings that were never reconciled: the interior layout, the plumbing schematic, and the tiling/finishes setting-out. For a bidet to install cleanly, all three have to agree on the same finished dimensions.

The four numbers to lock down

  • Finished back wall face. Mark it from the tiling schedule, including adhesive and tile thickness, not from the masonry line. Every set-out dimension for a back-fixed fixture runs from this face.
  • Waste centre and depth. Confirm whether the bidet waste is a floor outlet or a wall outlet, and record the centre distance from the finished wall. Trap type and rough-in must be read off the final technical sheet for the exact unit being ordered, not assumed from the series.
  • Cold and hot supply positions. Bidets need both supplies, unlike most WCs. Note their heights, offsets and whether they sit behind the fixture or in a chase beside it.
  • Clearance either side. A bidet needs usable elbow room. Fix the centre-to-centre distance to the WC and the clearance to any vanity or wall from the layout drawing, so the suite is not squeezed when a basin run changes.
Trap dimensions for the 1038 series are published per model on the technical sheet. The 1038A toilet, for example, lists an 180mm wall outlet rough-in for the P-trap option and a 250mm floor outlet rough-in for the S-trap option. Do not carry those figures across to the bidet by assumption — request the 1038F sheet with your order enquiry and reconcile it against the plumbing drawing.

A coordination sequence that works on site

The order below is the one we use when a bathroom package contains ceramics from several series. It keeps first-fix decisions off the critical path of the tiling programme.

StageWho actsWhat must be settled at this stage
Layout sign-offDesigner / clientRoom set-out, fixture list, which rooms take a bidet and which do not, suite series per bathroom type
Fixture schedule issueProcurement / contractorModel numbers per room type, quantities by floor or block, matching WC and basin series
Technical sheet returnSupplierOverall dimensions, fixing method, waste type and rough-in, supply requirements for each confirmed model
Plumbing coordinationMEP consultant / plumberWaste falls, supply positions, boxing and chase sizes, access panels
Finishes reconciliationInterior finishes / tilingFinished wall faces, floor build-up height, tile setting-out against fixture centres
Release for first fixSite managerSigned combined drawing; no ceramic order released before this point
Delivery and storageSupplier / siteDelivery sequence by bathroom, safe storage, pre-install inspection of each piece

The single most useful habit in that table is the last-but-two row: nothing ceramic gets released until one drawing shows plumbing centres and finishes faces together. It costs a week of coordination and saves a fortnight of chasing on site.

Specifying the bidet as part of a suite, not as an add-on

When a project specifies a matched sanitary look across many bathrooms, the schedule should name the series once and then list the pieces each room type takes. That is how hotel and apartment packages hold together commercially as well as visually: one ceramic body, one glaze, one spares profile for housekeeping.

  • Guest bathrooms with full hygiene provision: 1038F bidet paired with the matching 1038A two-piece washdown WC, plus the series basin and fittings.
  • Compact or accessible bathrooms: a wall-hung alternative such as the Wall Hung Bidet 1004F keeps the floor clear, which changes the waste route and the supporting frame — so it must be decided before first fix, not substituted afterwards.
  • Utility and guest WCs: WC only, no bidet. Record this explicitly so quantities do not drift when schedules are consolidated.

Freestanding and wall-hung bidets look similar on a rendered elevation and behave very differently in a riser. A back-fixed floor-standing unit takes its load at the floor and the back panel; a wall-hung unit needs a frame or carrier behind the finished wall. If your schedule mixes both, each bathroom type needs its own detail.

What to send us with an enquiry

Send these items together and we can confirm fit before you commit the order:

  • The fixture schedule or room-by-room list, with model numbers where already chosen.
  • Plumbing drawings showing waste and supply positions in finished dimensions.
  • The tiling or finishes schedule that establishes finished wall faces and floor build-up.
  • Project location, delivery address and how the goods will be received — pallet, crate, floor-level or kerbside.
  • Target programme dates for first fix and for handover.

With those documents we check the 1038F against your site conditions, flag any model that does not suit the arrangement shown, and quote the package as a suite rather than as loose items. As a furniture and building materials manufacturer working on villa, hotel and office projects, we supply ceramics like this alongside basins, showers, cabinetry, lighting and finishes, so one coordination round can close several trades at once — see our interior fixtures range for what else sits in the same package.

Receiving, storing and installing: the checks that protect the glaze

  • Inspect on arrival. Check every carton against the packing list and photograph any damage before signing. Ceramics travel a long way; damage claims need the paperwork at the point of delivery.
  • Store upright, dry and off the ground. Keep units in their cartons until installation day, in a room that has already been made watertight.
  • Dry-fit before sealing. Set the unit on its waste, check it sits plumb and stable against the finished wall, mark the fixings, then fit and seal. Do not rely on sealant alone to hold the body.
  • Connect hot and cold correctly and test flow. Run both supplies, check the mixer or taps balance, and confirm no leak at the waste joint before the surrounding finishes are signed off.
  • Protect after installation. If other trades are still working, keep the bowl covered and do not use abrasive cleaners on new glaze.

Common coordination failures, and how to avoid them

  • Bidet specified with no hot supply. Discovered after tiling. Fix: the fixture schedule must state supplies per fixture, not just positions.
  • Rough-in taken from the wrong model. Series names travel across drawings; trap dimensions do not. Fix: one technical sheet per ordered model, signed by the MEP reviewer.
  • Clearances lost to a longer vanity. The bidet becomes awkward to use. Fix: hold centre-to-centre dimensions on the layout drawing through every revision.
  • Floor build-up not accounted for. Waste falls run short. Fix: state the finished floor level, not the structural slab, on the plumbing drawing.
  • Late substitution from floor-standing to wall-hung. Requires a carrier that was never built. Fix: freeze vertical type per bathroom before first fix.

Send us your drawings and schedule. Share the fixture list, plumbing set-out and finishes schedule for your project, and we will confirm whether the Floor Standing Bidet 1038F suits the arrangement shown before you release the order. Contact PHILLIP on +86-13928214007 or santerson@qq.com, or use the contact page to start an enquiry.