A set of aluminium frame glass wardrobes is one of the most schedule-sensitive items in a villa or apartment project: it is made to measure, it combines metal frames with glass panels, and every unit has to arrive intact and fit the openings on site. This guide walks through the planning sequence we follow for international orders, from the specification freeze to the handover checklist, so the freight plan supports the site programme instead of fighting it.

Why This Order Class Is Different From Loose Furniture

Built-in joinery is not loose furniture. A sofa can be crated in standard cartons and replaced if it is damaged; a made-to-measure wardrobe cannot. Each unit is produced to the dimensions, layout and finish confirmed for that specific room, so a delay or a breakage does not simply mean a replacement box — it means re-manufacturing, re-shipping and an idle installation crew.

Two characteristics of these wardrobes drive the planning work:

  • Made-to-measure sizing. Dimensions are taken from the actual space, so any change to the wall build-up, flooring thickness or ceiling level after production starts has to be caught before it reaches the factory floor.
  • Mixed materials in one assembly. The aluminium frame, the glass infill and the solid or panelled interior are produced on different lines and assembled as one unit. Glass is the fragile element, so packaging and container loading plans are written around it.

SANTERSON is a China-based one-stop furniture and building materials supplier supplying project orders worldwide, with dedicated logistics coordinators handling freight forwarding by sea, air and rail. Because the same company produces the joinery and arranges the shipment, one team carries responsibility for both the production slot and the container plan.

Step 1: Lock the Specification Before the Production Slot

The single decision that shapes delivery time is when the specification is frozen. For an aluminium frame glass wardrobe order, a complete spec sheet covers:

Item to confirmWhy it matters for delivery
Room-by-room dimensions and levelsSets the manufacturing drawings; late dimensional changes restart production, not just shipping.
Glass type and finish (clear, bronze, smoked, frosted)Different glass stocks and surface treatments sit in different supply chains.
Frame profile and colourAnodised or powder-coated finishes add a processing stage to the frame line.
Door operation (sliding or hinged)Hardware sets, tracks and clearances are ordered per operation type.
Interior layout: drawers, shelves, hanging zonesDetermines part count per unit, which drives crate count and container volume.
Quantity per room typeRepeating layouts let us consolidate identical crates and simplify on-site assembly.

Our design and production coordination team works from the project brief, then confirms details against drawings before manufacturing begins. For projects that need a bespoke layout rather than a catalogue configuration, our custom and OEM service covers prototyping and material selection — wood, metals, engineered stone and laminates — so the specification is settled while there is still slack in the programme.

Step 2: Choose the Freight Mode Against the Site Programme

Work backwards from the date the installation crew needs the wardrobes on site, then allow time for each stage. The sequence we plan against is production and quality control, packaging and container loading, ocean or land leg, customs clearance, and final delivery to the project address.

  • Sea freight suits full project orders — a whole villa's joinery package, or several room types repeated across apartments. It carries the volume at the lower cost per cubic metre and pairs well with consolidated cabinetry, doors and wall panelling in one container.
  • Air freight suits small gap-fill quantities: a handful of units needed earlier than the main batch, or replacement parts after site inspection.
  • Rail is an option on corridors where it reaches the destination region faster than ocean while keeping cost below air. Availability depends on the delivery address.

Our logistics service covers freight forwarding, customs paperwork, packaging and container loading plans, shipment tracking and door-to-door delivery. The documentation package typically includes commercial invoices, packing lists, certificates of origin and any import permits the destination requires.

A note on terms: Incoterms, duties, insurance cover and transit arrangements are agreed per project. We do not quote a universal delivery time; the schedule is written for your destination port, order volume and building completion date.

Step 3: Pack and Load for Fragile Panels

The loading plan is decided at the packing stage, not at the port. For a project order we separate the shipment into crates that follow the room schedule, so an installation team can unpack one bedroom at a time rather than sorting a mixed container.

  • Framed crates with cushioned interiors for assembled units, with edge protection on the aluminium profiles.
  • Vertical racking for glass panels, kept upright through loading and stowage; flat stacking is avoided for large infill panels.
  • Hardware packed per unit and labelled against the crate marking, so nothing travels loose.
  • Crate numbering matched to the room schedule, printed on the packing list and cross-referenced to the drawings.

Container loading is planned around weight distribution and the fragile cargo: heavy solid-panel crates go on the floor, glass-bearing crates are secured and blocked so they cannot shift in transit. Cargo insurance can be arranged for the consignment when the project requires it.

Step 4: Clear Customs With Documents That Match the Cargo

Customs delays usually trace back to paperwork that does not describe what is in the crates. Before the shipment moves, we prepare the commercial invoice and packing list so descriptions, quantities and weights match the crate markings, together with the certificate of origin and any destination-specific import documentation.

For mixed project consignments — wardrobes travelling with built-in furniture, doors, wall panelling or sanitary ware — a single clear breakdown by product group makes assessment faster than one aggregated line. We recommend your clearing agent confirms the tariff classification for each group before loading, particularly where a project mixes joinery with metal and glass building products.

Step 5: Receive, Inspect and Install on Site

Delivery to the project address is the start of the fit-out phase, not the end of ours. A practical receiving routine on arrival day:

  • Count crates against the packing list before the carrier leaves, and photograph any damaged crate externally.
  • Open one complete room set first to check finish, glass condition and door operation while replacement is still possible.
  • Check openings against the drawings — floor levels, wall alignment and ceiling heights — before fixing any unit.
  • Record snags in writing with crate numbers and photographs, so spare parts or replacements are identified precisely.

Our installation and after-sales support covers on-site installation guidance, inspection and snag lists, warranty coverage and spare parts. Site coordination is arranged per project; the scope agreed in your contract sets what our team handles on site.

A Planning Checklist You Can drop Into a Project Programme

StageWhat has to be true before it starts
Specification freezeFinal room dimensions, glass and frame finishes, door operation and interior layout signed off.
Drawing confirmationFactory drawings cross-checked against the architectural and joinery drawings for the building.
Production and quality controlMaterials booked; frames, glass panels and interiors produced and assembled unit by unit.
Packaging and loading planCrate schedule complete; fragile-handling instructions issued to the loading team.
Main carriageBooking confirmed against the site programme; tracking shared with the project manager.
Customs clearanceDocuments aligned with crate contents; classification pre-confirmed by your clearing agent.
Delivery and handoverSite accessible, storage area prepared, receiving checklist assigned to a named person.

Where the same project also calls for other joinery in one shipment — glass walk-in wardrobes, kitchen cabinets, concealed doors or wall panelling — consolidating them with a single supplier means one production schedule, one packing list and one clearance file. That is how our turnkey interior project solutions keep a fit-out programme moving with fewer handovers between vendors.